A public-private
a city, county, and construction/management
company to attract a professional athletic
team to the area. Assume you are the engineer with
the company and are assisting with the benefit/cost
analysis. The primary options are to construct a
domed arena (DA) or a conventional stadium (CS),
one of which will definitely be built. The DA option
will cost $200 million to construct, have a useful
life of 50 years, and require M&O costs of
$360,000 the first year, increasing by $10,000 per
year thereafter. In 25 years, a remodeling expenditure
of $4,800,000 is predicted.
The CS option will cost only $50 million to construct,
have a useful life of 50 years, and require
M&O costs of $175,000 the first year, increasing
by $8000 per year. Periodic costs for repainting
and resurfacing for the stadium are estimated at
$100,000 every 10 years, except in year 50.
Revenue from DA is expected to be greater than
that from CS by $10,900,000 the first year, with
amounts increasing by $200,000 per year through
year 15. Thereafter, the extra revenue from the
dome is expected to remain constant at $13.7 million
per year. Assuming that both structures will have a
salvage value of $5 million, use an interest rate of
8% per year and a B/C analysis to determine which
structure should be built. Solve by hand or spreadsheet,
as instructed.
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 5 images
- The following data is provided for a PPP project. To the People To the Government Benefits $145,000 per year beginning now Cost $1.8 million now and $200,000 every 3 years Disbenefits $25,000 per year Savings $105,000 per year Calculate the conventional benefit/cost ratios using an interest rate of 9% per year and an infinite project period.arrow_forwardDefine the term Net Present Worth in the present worth analysis?arrow_forwardCost benefit analysis allows a business owner to identify the investment alternative with the highest return. True Falsearrow_forward
- A government-funded wind-based electric power generation company in the southern part of the country has developed the following estimates (in $1000) for a new turbine farm. The MARR is 10% per year and the project life is 25 years. Benefits: $45,000 in year 0; $29,500 in year 5 Government savings: $2,000 in years 1 through 20 Cost: $58,000 in year 0 Disbenefits: $3000 in years 1 through 10 NOTE: This is a multi-part question. Once an answer is submitted, you will be unable to return to this part. Calculate the PI value. The PI value isarrow_forwardThe sheriff of Los Lunas county along the Arizona- Mexico border asked the county to build a new minimum security detention facility for personscaught while attempting to enter the United States illegally. The construction cost will be $22 million, with annual operating costs of $2.1 million. The new facility will create jobs that produce benefits for many local businesses including realtors, restaurants, etc. The benefits are estimated to be $5 million in years 1 and 2, $2.8 million in year 3, and $1.12 million per year beginning in year 4 and continuing through the 30-year life of the facility. At a discount rate of 8% per year, does the conventional B/C ratio indicate that the project is economically justified?arrow_forwardThe B/C ratio for a flood control project along the Swanee River was calculated to be 1.1. If the benefits were $610,000 per year and the maintenance costs were $221,000 per year, determine the initial cost of the project at an interest rate of 11% per year and a 50- year life. The initial cost of the project is $arrow_forward
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education