A PCB assembly process supervisor wants to develop a standard time for a particular station of a new PCB model. The supervisor uses the standard 15% work time allowance factor. Determine the standard time of the process using the below-recorded observations. Hint: remove unusual time observations Station Element Insert Component A Insert Component B Insert Component C Insert Component D 1 100 60 204 20 2 180 65 155 25 Observed Time (seconds) 3 102 61 159 21 4 103 60 150 70 5 101 64 154 85 6 100 68 153 26 Performance Rating 90% 110% 95% 100%

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Determine the standard time of the process using the below-recorded observations.

Hint: remove unusual time observations

Problem #4
A PCB assembly process supervisor wants to develop a standard time for a particular station of
a new PCB model. The supervisor uses the standard 15% work time allowance factor.
Determine the standard time of the process using the below-recorded observations.
Hint: remove unusual time observations
Station
Element
Insert
Component A
Insert
Component B
Insert
Component C
Insert
Component D
1
100
60
204
20
2
180
65
155
25
Observed Time (seconds)
3
102
61
159
21
4
103
60
150
70
5
101
64
154
85
6
100
68
153
26
Performance
Rating
90%
110%
95%
100%
Transcribed Image Text:Problem #4 A PCB assembly process supervisor wants to develop a standard time for a particular station of a new PCB model. The supervisor uses the standard 15% work time allowance factor. Determine the standard time of the process using the below-recorded observations. Hint: remove unusual time observations Station Element Insert Component A Insert Component B Insert Component C Insert Component D 1 100 60 204 20 2 180 65 155 25 Observed Time (seconds) 3 102 61 159 21 4 103 60 150 70 5 101 64 154 85 6 100 68 153 26 Performance Rating 90% 110% 95% 100%
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.