A foundation with dimensions BxL supporting a column load, P. The foundation rests on a sandy soil underlain by a clay layer (consolidation test result in Problem 2). • Estimate the primary consolidation settlement of the clay due to the foundation load. • What is the void ratio at the end of primary consolidation? • Calculate the secondary Consolidation settlement after 6 years knowing that the primary consolidation settlement took 2.5 years. Given: P = 350 kN, B = L = 2.5 m, D= 2 m, H₁= 3 m, and H₂=4.5 m. The soil properties are as follows: Sand: ya = 16.4 kN/m³; Ysat = 18.8 kN/m³ Clay: Ysat = 17.6 kN/m³; eo = 0.82, Ca=0.02 D₁ GWT--!. BXL Ysat Clay Ysat Sand Yd Sandy gravel H₁

Principles of Foundation Engineering (MindTap Course List)
8th Edition
ISBN:9781305081550
Author:Braja M. Das
Publisher:Braja M. Das
Chapter2: Geotechnical Properties Of Soil
Section: Chapter Questions
Problem 2.14P
icon
Related questions
Question
A foundation with dimensions BxL supporting a column load, P. The foundation rests on a
sandy soil underlain by a clay layer (consolidation test result in Problem 2).
• Estimate the primary consolidation settlement of the clay due to the foundation load.
• What is the void ratio at the end of primary consolidation?
• Calculate the secondary Consolidation settlement after 6 years knowing that the primary
consolidation settlement took 2.5 years.
Given:
P = 350 kN, B =L=2.5 m, Df= 2 m, H1= 3 m, and H2=4.5 m.
The soil properties are as follows:
Sand: ya = 16.4 kN/m³; ysat = 18.8 kN/m³
Clay: Ysat = 17.6 kN/m²; eo = 0.82, Ca=0.02
Sand
D
Yd
H
GWT
BxL
Ysat
Clay
Ysat
Sandy gravel
Transcribed Image Text:A foundation with dimensions BxL supporting a column load, P. The foundation rests on a sandy soil underlain by a clay layer (consolidation test result in Problem 2). • Estimate the primary consolidation settlement of the clay due to the foundation load. • What is the void ratio at the end of primary consolidation? • Calculate the secondary Consolidation settlement after 6 years knowing that the primary consolidation settlement took 2.5 years. Given: P = 350 kN, B =L=2.5 m, Df= 2 m, H1= 3 m, and H2=4.5 m. The soil properties are as follows: Sand: ya = 16.4 kN/m³; ysat = 18.8 kN/m³ Clay: Ysat = 17.6 kN/m²; eo = 0.82, Ca=0.02 Sand D Yd H GWT BxL Ysat Clay Ysat Sandy gravel
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps

Blurred answer
Knowledge Booster
Calculation of settlement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning