A flexible pavement construction project is proposed. The estimated service life is 20 years. The initial cost is estimated at $205,000, and it would have a salvage value of $34,000 at the end of its useful life. The yearly maintenance is estimated at $2,505. What would be the present worth of life-cycle costs? What will be the user cost savings annually to justify the pavement construction ? Use interest rate of 5%.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter11: Capital Budgeting Decisions
Section: Chapter Questions
Problem 3EA: If a copy center is considering the purchase of a new copy machine with an initial investment cost...
icon
Related questions
Question
A flexible pavement construction project is proposed. The estimated service life is 20 years. The initial cost is estimated at $205,000, and it would have a salvage value of $34,000 at the end of its useful life. The yearly maintenance is estimated at $2,505. What would be the present worth of life-cycle costs? What will be the user cost savings annually to justify the pavement construction ? Use interest rate of 5%.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Rate Of Return
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College