Question
Using the following project information
Activity
|
Optimistic Time
Estimate(weeks) |
Most Likely Time
Estimates (weeks) |
Pessimistic Time
Estimates (weeks) |
Immediate
Predecessor(s) |
||||
---|---|---|---|---|---|---|---|---|
A
|
2 | 3 | 5 | none | ||||
B
|
2.6 | 4 | 5 | A | ||||
C
|
5 | 7 | 8 | A | ||||
D
|
3 | 5 | 7 | B, C | ||||
E
|
4 | 7 | 14 | B, C | ||||
F
|
2 | 5 | 8 | D | ||||
G
|
4 | 5 | 6 | E | ||||
H
|
6 | 6 | 7 | F | ||||
I
|
4 | 7 | 10 | G | ||||
J
|
2 | 3 | 3 | H, I |
The critical path is A-C-E-G-I-J.
Activity
|
A
|
B
|
C
|
D
|
E
|
F
|
G
|
H
|
I
|
J
|
---|---|---|---|---|---|---|---|---|---|---|
Variance
|
0.25 | 0.16 | 0.25 | 0.44 | 2.78 | 1.00 | 0.11 | 0.03 | 1.00 | 0.03 |
(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project ≤ 31) = enter a probability
(b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project ≤ 35) = enter a probability
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1 ES FF LS A (3) 1 0 Activity (Duration) EF TF LF 4 4 40 11 FF 5 4 B (3) 7 5 14 G (6) 40 1. What is the LF for Activity F? 2. What is the ES for Activity H? 3. What is the LS for Activity C? 4. What is the FF for Activity G? 7 14 E (4) 10 10 FS5 9 18 SS 3 SF 6 C (1) H (11) 0 F (7) FS 2 D (2)arrow_forwardGiven an activity's optimistic, most likely, and pessimistic time estimates of 4, 22, and 28 days respectively, compute the PERT expected activity time for this activity. 7 22 20 none of these 18arrow_forward0 1 11. Given the time-phased work packages and network, complete the baseline budget form for the project. Soccer Toy Project 3 Order parts Design prototype 2 2 Build prototype Prepare production Assemble & test 2 3 Legend ES ID EF 5 SL Description Prepare marketing LS DUR LF 5 Soccer Toy Project Cost by Week ($000) +1-2-3-4-5 Design prototype Build prototype Order parts 12 10 10 10 5 5 Prepare production 16 10 22 Prepare marketing 6 6 о 6 12 Assemble & test 18 18 Launch 12 Time-phased Budget ($000) Week 1 2 5 6 8 11 12 13 Budget Design prototype 24 Build prototype 30 10 ° Order parts Prepare 64 prod'n Prepare market'g 30 Assemble 36 & test Launch Total 206 Cumulative Launcharrow_forward
- Time Immediate Time Immediate Activity (weeks) Predecessor(s) Activity (weeks) Predecessor(s) A 7 4 7 B 3 11 C, E 1 7 D.F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF 7 B 10 7 E 11 G 22 20 Dave's latest start (LS) and latest finish (LF) are: Activity LS LF H 15 G 11 F 9 E 7 D 14 A The slack times are: Activity Slack A D E F G H The activities on the critical path are The total project completion time for Dave = weeks.arrow_forwardanswer into tablearrow_forwardActivity Predecessor Estiumated time Aij A=(1-2) - 2 4 6 B=(2-4) A 4 7 10 C=(2-3) A 6 7 14 D=(2-5) A 3 6 9 E=(4-6) B,C 12 14 22 F=(3-5) C 2 10 12 G=(5-6) D,F 6 9 12 H=(6-7) E,G 5 7 15 -Calculate the Expected Time (te)-Calculate the Variance (vt)-Calculate the Standard Deviation (St)arrow_forward
- Using the following table, calculate the project duration Task Predecessor Duration (weeks) A - 1 B A 2 C - 2 D - 3 E B 3 F C, D 4 G E,F 6 H F 1arrow_forward. Assume that a project has an expected total duration of 25 days, but several optimistic employees feel that it can be completed in as little as 18 days, while others expect it to take nearly 40 days. Using program evaluation and review technique calculations, what is the project duration to be used in project Gantt charts and other tracking tools?2. If a critical path method calculation of project duration was 25 days, how does the program evaluation and review technique calculation in Question 1 compare?arrow_forwardMueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 45-week completion date requested by the owner. The Mueller project manager prepared the following project network. Start A B F H 0 D E Finish Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable A 4 8 Pessimistic 12 B 6 7 8 C 6 12 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 6 13arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.