A bill of quantity of a project includes 500m2 of masonry work. The work will be done by one crew with a production rate of 50 m2/day and consists of: Crew member No Price rate Brick layer 2 50$/day Assistant 1 25 Labor 2 12 Vendor price of 1000 bricks = 160$. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m2 and consists of: Quantity Material Primary quotation form vendor One cubic meter Sand 15$/m3 6 sacks (50 kg each) Cement 240$/ton As a contractor, it is required to estimate the work unit price and the work price. Assume all material waste as 10% and assume overheads and markup as 20% of total cost. (WRITE THE ANSWER ONLY)
A bill of quantity of a project includes 500m2 of masonry work. The work will be done by one crew with a production rate of 50 m2/day and consists of: Crew member No Price rate Brick layer 2 50$/day Assistant 1 25 Labor 2 12 Vendor price of 1000 bricks = 160$. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m2 and consists of: Quantity Material Primary quotation form vendor One cubic meter Sand 15$/m3 6 sacks (50 kg each) Cement 240$/ton As a contractor, it is required to estimate the work unit price and the work price. Assume all material waste as 10% and assume overheads and markup as 20% of total cost. (WRITE THE ANSWER ONLY)
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
A bill of quantity of a project includes 500m2 of masonry work. The work will be done by one crew with a production rate of 50 m2/day and consists of:
Crew member |
No |
Price rate |
Brick layer |
2 |
50$/day |
Assistant |
1 |
25 |
Labor |
2 |
12 |
Vendor price of 1000 bricks = 160$. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m2 and consists of:
Quantity |
Material |
Primary quotation form vendor |
One cubic meter |
Sand |
15$/m3 |
6 sacks (50 kg each) |
Cement |
240$/ton |
As a contractor, it is required to estimate the work unit price and the work price. Assume all material waste as 10% and assume overheads and markup as 20% of total cost. (WRITE THE ANSWER ONLY)
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning