532 ELEV (FT) BORING M-1 Nc (B/FT) FOOTING 5 FT x 5 FT CROSS-SECTION VIEW EAST Q = 150 KIPS DOES NOT INCLUDE FOOTING 4 FT TOPSOIL: 3 FT 528 2 - 2 FT THICK 5 FT - YT = 124 LB/FT³ 12 SILTY SAND EL 525.5 FT XI = 112.4 LB/FT3 A FOOTING 12 w = 9.4% Gs = 2.65 - 3 FT THICK 0 4 15 -#200 = 2.0% 518 10 SCALE (FT) 14 SAND AND GRAVEL XE 133.6 LB/FT³ w = 12.8 % 14 Gs = 2.65 -# 200 10.8% 50/1 IN. 506 EL 512 FT B GLACIAL TILL GROUND SURFACE ELEVATION: 532 FT ELEVATION POINT A: 525.5 FT (5) DEPTH OF SOIL AT POINT A: FT 3. CAREFULLY STUDY THE GEOTECHNICAL PROFILE FOR A BUILDING PROJECT IN THE PORTLAND, OREGON AREA. DETERMINE THE FOLLOWING: (24) 3A. TOTAL VERTICAL STRESS IN THE SOIL AT POINT A, PRIOR TO CONSTRUCTION: OVA = OVA = OVA 7 | Page

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
532
ELEV (FT)
BORING M-1
Nc (B/FT)
FOOTING
5 FT x 5 FT
CROSS-SECTION
VIEW EAST
Q = 150 KIPS DOES NOT
INCLUDE FOOTING
4 FT
TOPSOIL:
3 FT
528
2
- 2 FT THICK
5 FT
- YT
= 124 LB/FT³
12
SILTY SAND
EL 525.5 FT
XI
= 112.4 LB/FT3
A
FOOTING
12
w = 9.4%
Gs = 2.65
- 3 FT THICK
0
4
15
-#200 = 2.0%
518
10
SCALE (FT)
14
SAND AND GRAVEL
XE
133.6 LB/FT³
w = 12.8 %
14
Gs = 2.65
-# 200 10.8%
50/1 IN.
506
EL 512 FT
B
GLACIAL TILL
GROUND SURFACE ELEVATION: 532 FT
ELEVATION POINT A: 525.5 FT
(5) DEPTH OF SOIL AT POINT A:
FT
3. CAREFULLY STUDY THE GEOTECHNICAL PROFILE FOR A BUILDING PROJECT
IN THE PORTLAND, OREGON AREA. DETERMINE THE FOLLOWING:
(24) 3A. TOTAL VERTICAL STRESS IN THE SOIL AT POINT A, PRIOR TO
CONSTRUCTION:
OVA =
OVA =
OVA
7 | Page
Transcribed Image Text:532 ELEV (FT) BORING M-1 Nc (B/FT) FOOTING 5 FT x 5 FT CROSS-SECTION VIEW EAST Q = 150 KIPS DOES NOT INCLUDE FOOTING 4 FT TOPSOIL: 3 FT 528 2 - 2 FT THICK 5 FT - YT = 124 LB/FT³ 12 SILTY SAND EL 525.5 FT XI = 112.4 LB/FT3 A FOOTING 12 w = 9.4% Gs = 2.65 - 3 FT THICK 0 4 15 -#200 = 2.0% 518 10 SCALE (FT) 14 SAND AND GRAVEL XE 133.6 LB/FT³ w = 12.8 % 14 Gs = 2.65 -# 200 10.8% 50/1 IN. 506 EL 512 FT B GLACIAL TILL GROUND SURFACE ELEVATION: 532 FT ELEVATION POINT A: 525.5 FT (5) DEPTH OF SOIL AT POINT A: FT 3. CAREFULLY STUDY THE GEOTECHNICAL PROFILE FOR A BUILDING PROJECT IN THE PORTLAND, OREGON AREA. DETERMINE THE FOLLOWING: (24) 3A. TOTAL VERTICAL STRESS IN THE SOIL AT POINT A, PRIOR TO CONSTRUCTION: OVA = OVA = OVA 7 | Page
Expert Solution
steps

Step by step

Solved in 1 steps

Blurred answer
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning