41. A borrow pit soil has a dry density of 17 kN/m³. How many cubic meters of this soil will be required to construct an embankment of 100 m³ volume with a dry density of 16 kN/m³ O A. 94 m³ O B. 106 m3 O C. 100 m³ O D. 90 m³

Principles of Foundation Engineering (MindTap Course List)
8th Edition
ISBN:9781305081550
Author:Braja M. Das
Publisher:Braja M. Das
Chapter16: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 16.12P
icon
Related questions
icon
Concept explainers
Question
41. A borrow pit soil has a dry density of 17 kN/m³. How many cubic meters of this soil
will be required to construct an embankment of 100 m³ volume with a dry density
of 16 kN/m³
O A. 94 m³
O B. 106 m³
O C. 100 m³
O D. 90 m³
Transcribed Image Text:41. A borrow pit soil has a dry density of 17 kN/m³. How many cubic meters of this soil will be required to construct an embankment of 100 m³ volume with a dry density of 16 kN/m³ O A. 94 m³ O B. 106 m³ O C. 100 m³ O D. 90 m³
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Sediment transport
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning