Question
27. Consider a project with six activities: G, B, C, D, E, and F. Assume G and F can be started as soon as the project is kicked off. B can start as soon as G is completed, C can start as soon as both G and F are completed. D will start as soon as both B and C are completed. E will start as soon as D finishes. Which of the following choices is the correct collection of immediate precedence relationships in the project network?
G--> B, F--> C, B --> D, C--> E, D--> E, F--> D |
||
G--> B, G--> C, B --> D, C--> D, D--> E, F--> C |
||
G--> B, G--> C, B --> D, C--> D, D--> E, D--> F |
||
None of choices |
||
G--> B, F--> C, B --> D, C--> D, D--> E, F--> D |
||
G--> B, G--> C, B --> D, C--> D, D--> E, D--> F |
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1. A project was planned using PERT with three-time estimates. The expected completion time of the project was determined to be 40 weeks. The variance of the critical path is 9. (e) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date. What should this due date be?arrow_forwardConsider the precedence network diagram. The numbers above the nodes represent activity durations (in days). End 13 Suppose that after 12 days, activities 1, 9, and 2 have been finished; activity 3 is 75 percent finished; and activity 10 is half finished. How many days after the original start time would the project finish? The project should finish ]days from the start.arrow_forwardWe reduce Activity B to 4 weeks on each of the six houses.What affect will that have on the project completion time? Show work on the template provided. The x axis is the number of houses The y axis is time (number of weeks)arrow_forward
- Consider a project with four activities. Activities A1, A2, and A3 all can start immediately.However, A4 requires the completion of A1, A2, and A3. A1 can take any time between4 and 8 days. A2 can take any time between 2 and 6 days. A3 always takes 5 days. Inaddition to A4, which activity (or activities) has the potential to be on the critical path?a. A1b. A1 and A2c. A2 and A3d. A1, A2, and A3e. None of these options is correctarrow_forward50 The phases of project management are: Select one: a. different for manufacturing projects than for services projects b. GANTT, CPM, and PERT c. planning, organizing, staffing, leading and controlling d. planning, programing, and budgeting e. planning, scheduling, and controllingarrow_forwardTo help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. A project network with 10 activities and 13 directed arcs is shown. Activity Start is connected to activity A and to activity B. Activity A is connected to activity C and to activity D. Activity B is connected to activity E. Activity C is connected to activity H. Activity D is connected to activity F and to activity G. Activity E is connected to activity F and to activity G. Activity F is connected to activity H. Activity G is connected to activity Finish. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. The following table lists the activity time estimates (in weeks) for each activity. Activity Optimistic Most Probable Pessimistic A 4 5 6 B 2.5 3 3.5 C 5 6 7 D 5 5.5 9 E 5 7 9 F 2 3 4 G 9 11 13 H 7 8 15 Based only on the critical path, what is the estimated probability…arrow_forward
- 12. In general, work packages should not exceed 10 work days. 13. The project structure chosen to manage the project will have little impact on the actual project work to be accomplished. 14. An activity is an element of the project that always requires time but may or may not require resources. 15. The forward pass through a project network determines the critical path. 16. Different activities along the same path can have different total slack. 17. It is possible to have more than one critical path at the same time. 18. Free slack applies to an entire project network. 19. Lags are used to break larger activities into smaller segments so that activities that follow can be started earlier. 20. In a balanced matrix form of project management, the project manager is responsible for defining what needs to be accomplished while the functional managers are concerned with how it will be accomplished.arrow_forwardThere are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 100 hours. The maximum possible reduction in the project duration will be: a. Insufficient information b. 1300 hours c. 500 hours d. 400 hours e. 600 hourarrow_forwardA simple CPM network has three activities, N, O, and P. N is an immediate predecessor of O and of P. O is an immediate predecessor of P. The activity durations are N = 9, 0 = 7, P = 5. O A. The critical path is N-O-P, duration 21. O B. The network has no critical path. O C. The critical path is O-P, duration 12. D. The critical path is N-P, duration 14. O E. The critical path is N-O-P, duration 7.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.