Question
20
Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?
Select one:
a. The set of times cannot all be possible.
b. S is a critical activity.
c. R has no slack but is not critical
d. N is a critical activity
e. R is critical and has zero slack
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 10. The late start time for an activity is equal to the late finish time minus the activity time. True Falsearrow_forwardA Gantt chart is a project schedule that superimposes project activities on a time line. Part 2 True Falsearrow_forwardConsider a project that has the following tasks (with the duration measured in days): Task ID Duration Dependency A 3 14 C,F a) Draw the PERT chart for the above table. Be sure to include sequencing and identification for all tasks and events along with their time estimates. b) What is the critical path. c) What is the total expected duration time represented by the critical path. earrow_forward
- Discuss the suggestion of preparing short-interval schedules 1 week prior to discussing them at a project meeting in order for all personnel to have ample time to review the information.arrow_forwardThe extent of time by which an activity can be delayed beyond its earliest start time without extending the project is_____ Oa. Slack time O b. Latest start time Oc Optimistic time Od. Expected start timearrow_forwardIn the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) A B с A A B B C D E, F Carl's team should be able to complete the project in F G H days. Time (days) 3 4664469arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.