2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily resources needed to no more than 8 laborers per day. If you cannot get it down to 8, manually shift resources so that the project starts low and gradually increases towards the middle and gradually decreases toward the end of the project. Activity A B C D E חן ד F G I J Duration (days) 6 2 9 4 7 5 10 8 3 2 IPA A, B B D D, E C, F, G C, G H, I laborers 2 3 3343 4 2 2 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
2. For the following project draw a node network and a bar chart. Then perform resource
leveling trying to reduce the daily resources needed to no more than 8 laborers per day.
If you cannot get it down to 8, manually shift resources so that the project starts low
and gradually increases towards the middle and gradually decreases toward the end of
the project.
Activity
A
B
C
D
E
ח| ד
F
G
H
I
J
Duration (days)
6
2
9
4
7
5
10
832
IPA
A, B
B
D
D, E
C, F, G
C, G
H, I
laborers
2
3
33
4
2
3
1
22
2
Transcribed Image Text:2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily resources needed to no more than 8 laborers per day. If you cannot get it down to 8, manually shift resources so that the project starts low and gradually increases towards the middle and gradually decreases toward the end of the project. Activity A B C D E ח| ד F G H I J Duration (days) 6 2 9 4 7 5 10 832 IPA A, B B D D, E C, F, G C, G H, I laborers 2 3 33 4 2 3 1 22 2
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,