1. Calculate PERT weighted average for each activity. Show the formula you used and calculations below then fill in the table with the corresponding estimated duration. 2. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. 3. Identify all the paths on the network diagram and calculate their lengths. 4. What is the critical path for this project and how long is it?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
I want solve with step
Question 3:
Consider the table below for Question 1 and 2. All
duration estimates, or estimated times are in days,
and the network proceeds from Node 1 to Node 9.
Activity Initial Node Final Node
A
B
C
D
E
F
G
H
|
J
K
1
1
2
2
3
4
5
5
6
7
8
2
3
4
5
6
7
7
8
7
9
9
Estimated Duration
O MP PERT
1 47
1
23
3
5 7
4
6 8
2 3 4
2
2
1
4
3
3
58
4 6
2 3
79
4 5
6 9
1. Calculate PERT weighted average for each activity.
Show the formula you used and calculations below
then fill in the table with the corresponding estimated
duration.
2. Draw an AOA network diagram representing the
project. Put the node numbers in circles and draw
arrows from node to node, labeling each arrow with the
activity letter and estimated time.
3. Identify all the paths on the network diagram and
calculate their lengths.
4. What is the critical path for this project and how long
is it?
Transcribed Image Text:Question 3: Consider the table below for Question 1 and 2. All duration estimates, or estimated times are in days, and the network proceeds from Node 1 to Node 9. Activity Initial Node Final Node A B C D E F G H | J K 1 1 2 2 3 4 5 5 6 7 8 2 3 4 5 6 7 7 8 7 9 9 Estimated Duration O MP PERT 1 47 1 23 3 5 7 4 6 8 2 3 4 2 2 1 4 3 3 58 4 6 2 3 79 4 5 6 9 1. Calculate PERT weighted average for each activity. Show the formula you used and calculations below then fill in the table with the corresponding estimated duration. 2. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. 3. Identify all the paths on the network diagram and calculate their lengths. 4. What is the critical path for this project and how long is it?
Expert Solution
steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.