Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 9.8, Problem 18P
a.
Summary Introduction
Interpretation: A sequence required for the planes landing with an objective of minimizing the expected average weighted flow time must be prepared.
Concept Introduction:
Probability: Probability is the chance of an event occurring. A number of favorable outcomes must be divided by the total number of possible outcomes to get the probability factor.
b.
Summary Introduction
Interpretation: Theprobability of planes landing with 100 minutes has to be calculated.
Concept Introduction:
Probability: Probability is the chance of an event occurring. A number of favorable outcomes must be divided by the total number of possible outcomes to get the probability factor.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The maintenance department of an Oil and Gas Company has 6 large drilling equipment waiting for repairs. These are labelled A, B, C, D, E and F. The respective repair times (in days) and the remaining days before the due date are given in the table below.
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 What is the direct labor content (in seconds per unit)?
Consider two different workstations. Each workstation consists of machines A and B,
respectively. Machine A has a mean effective process time of 1.0 hours and an c² of 0.25.
Machine B has a mean effective process time of 0.85 hour and an c² of 4. Assume the part
arrival and service processes follow a general distribution.
1
(a) For an arrival rate of 0.92 job per hour with c2 = 1, which machine will have a shorter
average cycle time?
(b) Now put one more machine of type A at the station and double the arrival rate (i.e.,
double the capacity and the throughput). What happens to cycle time?
Chapter 9 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 9.5 - Prob. 1PCh. 9.5 - Prob. 2PCh. 9.5 - Prob. 3PCh. 9.5 - Prob. 4PCh. 9.5 - Prob. 5PCh. 9.6 - Prob. 6PCh. 9.6 - Prob. 7PCh. 9.6 - Prob. 8PCh. 9.6 - Prob. 9PCh. 9.6 - Prob. 10P
Ch. 9.7 - Prob. 11PCh. 9.7 - Prob. 12PCh. 9.7 - Prob. 13PCh. 9.7 - Prob. 14PCh. 9.7 - Prob. 15PCh. 9.7 - Prob. 16PCh. 9.7 - Prob. 17PCh. 9.8 - Prob. 18PCh. 9.8 - Prob. 19PCh. 9.8 - Prob. 20PCh. 9.8 - Prob. 21PCh. 9.8 - Prob. 22PCh. 9.9 - Prob. 23PCh. 9.9 - Prob. 24PCh. 9.9 - Prob. 25PCh. 9.10 - Prob. 27PCh. 9.10 - Prob. 28PCh. 9.10 - Prob. 29PCh. 9 - Prob. 30APCh. 9 - Prob. 31APCh. 9 - Prob. 32APCh. 9 - Prob. 33APCh. 9 - Prob. 34APCh. 9 - Prob. 35APCh. 9 - Prob. 36APCh. 9 - Prob. 37APCh. 9 - Prob. 38APCh. 9 - Prob. 39APCh. 9 - Prob. 40APCh. 9 - Prob. 41APCh. 9 - Prob. 42APCh. 9 - Prob. 43APCh. 9 - Prob. 44APCh. 9 - Prob. 45APCh. 9 - Prob. 46APCh. 9 - Prob. 47AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Problem#1: Arrivals of a customers to payment counter in a bank follow poisson distribution with an average of 10 per hour. The service time follows negative exponential distribution with an average of 4 minutes.(a) What is the average number of customers in the Queue?(b) The bank will open one or more counter when the waiting time of a customer is at least 10 minutes. By how much the flow of arrivals should increase in order to justify the second counter?arrow_forwardFive jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta R 20 10 S 25 30 T 30 20 U 35 35 V 15 25 Part 2 A. V−S−U−T−R B. V−R−U−S−T C. R−V−T−S−U D. S−U−T−V−R E. R−S−T−U−Varrow_forwardThe 4M company has a lathe as the centerpiece of the plant's work. The jobs arrive according to a Poisson process with an average rate of 2 per day. The processing time of each job is exponentially distributed with an average of 1/ 4 day. Since the jobs are large, if they are not in process they are stored in a warehouse some distance from the machine. However, to save time in bringing them in, the production manager proposes to add space for 3 in-process jobs in addition to the one on the lathe (the rest will continue to be stored). With this proposal, what proportion of the time will the space next to the lathe be adequate for the waiting jobs? Calculate your answer using the formulas available.arrow_forward
- A process improvement team is working to improve the production output at the Johnson Manufacturing plant’sHeader Cell that manufactures a key component, headers, used in commercial air conditioners. A header is partof the circulatory system of a commercial air conditioner that moves coolant between various components suchas the evaporator coil and the condenser coil. Currently, the header production cell is scheduled separately fromthe main work in the plant. Often, individual headers are not sequenced to match the product they go into on thefinal assembly line in a timely fashion, and so the product can sit in queue waiting for a headerarrow_forwardProblem 2: Suppose you observe the following arrivals and departures from a single-server queueing system. Observations begin at time 100.0 (with no one in the queue) and end at 120.0. Customer Time Customer # Arrives to Queue 83 84 85 86 87 88 89 90 91 100.4 101.5 105.1 106.8 108.1 113.5 117.9 118.0 119.9 Time Customer Departs from Queue and Goes Into Service 102.3 108.3 109.5 110.6 112.9 114.2 117.9 119.2 After 120.0 Time Customer Departs From Server 108.3 109.5 110.6 112.9 114.2 116.3 119.2 After 120.0 After 120.0 1) What is the sample mean, sample standard deviation, minimum, and maximum of the waiting time in the queue observed for the customers who arrived at, and departed from, the queue during the time interval [100.0, 120.0]?arrow_forwardA shipping company operates 10 container ships that can each carry 5000 containers oneach journey between ports. They want to be able to load and unload 20,000 containerseach week. Assume their ships always travel fully loaded. What is the longest averagetravel time between ports that allows them to meet their goal of 20,000 containers perweek?arrow_forward
- Using the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received. Carrow_forward7. The manager of a regional warehouse must decide on the number of loading docks to request fora new facility in order to minimize the sum of dock costs and driver-truck costs. The manager haslearned that each driver-truck combination represents a cost of $300 per day and that each dockplus loading crew represents a cost of $1,100 per day.a. How many docks should be requested if trucks arrive at the rate of three per day, each dockcan handle five trucks per day, and both rates are Poisson?b. An employee has proposed adding new equipment that would speed up the loading rate to 6trucks per day. The equipment would cost $100 per day for each dock. Should the managerinvest in the new equipment?arrow_forwardOne possible solution method for the machine-to job assignment problem is the following heuristic procedure. Assign the machine to job 1 that completes job 1 quickest. Then assign the machine to job 2 that, among all machines that still have some capacity, completes job 2 quickest. Keep going until a machine has been assigned to all jobs. Does this heuristic procedure yield the optimal solution for this problem? If it does, see whether you can change the job times so that the heuristic does not yield the optimal solution.arrow_forward
- of There are three work centers (A, B, and C) in a factory that can each fit into three spaces (1, 2, and 3) off the corridor behind the processing equipment. The distance from 1-2 is 10 feet, 2-3 is 30 feet, and 1-3 is 40 feet. The matrix of work (trips per day) at the three centers are shown in the following table. Assume that each trip must be a round-trip (from 1 to 2 and back, for example). Find the optimal assignment that minimizes distance traveled. any B. A. 20 50 B. 30 OA-1, B-2, C-3 A-2, B-3, C-1 A-3, B-2, C-1 O A-1, B-3, C-2 A-2, B-1, C-3arrow_forwardDiablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and assembledin five different workstations (V, W, X, Y, and Z) using a small batch process. Each workstation is staffedby a worker who is dedicated to work a single shift per day at an assigned workstation. Batch setuptimes have been reduced to such an extent that they can be considered negligible. A flowchart denotesthe path each product follows through the manufacturing process as shown in Figure 5.2, where eachproduct’s price, demand per week, and processing times per unit are indicated as well. Inverted trianglesrepresent purchased parts and raw materials consumed per unit at different workstations. Diablo canmake and sell up to the limit of its demand per week, and no penalties are incurred for not being able tomeet all the demand.Which of the five workstations (V, W, X, Y, or Z) has the highest utilization, and thus serves as the bottle-neck for Diablo Electronics?arrow_forwardCan someone help me to fully solve the following question neatly.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.