Pinnacle Corp. budgeted $256,440 of overhead cost for the current year. Actual overhead costs for the year were $247,850. Pinnacle's plantwide allocation base, machine hours, was budgeted at 51,170 hours. Actual machine hours were 55,880. A total of 108,410 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is: Oa. $5.01 per machine hour Ob. $4.84 per machine hour Oc. $2.37 per machine hour Od. $2.29 per machine hour

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 1EA: Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Question Content Area

Given the following information, determine the activity rate for setups.

Activity Total Activity-Base Usage Budgeted Activity Cost
Setups 10,100             $63,200            
Inspections 24,100             $137,300            
Assembly (dlh) 72,000             $400,600            
Pinnacle Corp. budgeted $256,440 of overhead cost for the current year. Actual overhead costs for the year were $247,850. Pinnacle's plantwide allocation base, machine hours,
was budgeted at 51,170 hours. Actual machine hours were 55,880. A total of 108,410 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's
plantwide factory overhead rate for the current year is:
Oa. $5.01 per machine hour
Ob. $4.84 per machine hour
Oc. $2.37 per machine hour
Od. $2.29 per machine hour
Transcribed Image Text:Pinnacle Corp. budgeted $256,440 of overhead cost for the current year. Actual overhead costs for the year were $247,850. Pinnacle's plantwide allocation base, machine hours, was budgeted at 51,170 hours. Actual machine hours were 55,880. A total of 108,410 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is: Oa. $5.01 per machine hour Ob. $4.84 per machine hour Oc. $2.37 per machine hour Od. $2.29 per machine hour
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning