Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1650000 each quarter. The total contract price is $18762000 and Oriole estimates total costs of $17900000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, Oriole Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18100000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2022 for Oriole as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit?   Difference between the accounts   Debit/Credit $871500   Credit $4690500   Credit $871500   Debit $375000   Debit

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 13E: On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million....
icon
Related questions
Question
Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1650000 each quarter. The total contract price is $18762000 and Oriole estimates total costs of $17900000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2021.

At December 31, 2022, Oriole Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18100000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2022 for Oriole as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit?

  Difference between the accounts   Debit/Credit

$871500   Credit
$4690500   Credit
$871500   Debit
$375000   Debit
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning