Haliburton Mills Inc. is a large producer of men's and women's clothing. The company uses standard costs for all of its products. The standard costs and actual costs for a recent period are given below for one of the company's product lines (per unit of product): Standard Actual Cost Cost Direct materials: Standard: 4.0 metres at $4.60 per metre Actual: 4.2 metres at $4.40 per metre Direct labour: $18.40 $18.48 Standard: 2.4 hours at $4.50 per hour Actual: 2.2 hours at $4.85 per hour 10.80 10.67 Variable manufacturing overhead: Standard: 2.4 hours at $2.20 per hour Actual: 2.2 hours at $2.55 per hour 5.28 5.61 Fixed manufacturing overhead: Standard: 2.4 hours at $3.80 per hour Actual: 2.2 hours at $3.85 per hour Total cost per unit 9.12 8.47 $43.60 $43.23 Actual costs: 5,000 units at $43.23 Standard costs: 5,000 units at $43.60 Difference in cost-favourable $216,150 218,000 $ 1,850 During this period, the company produced 5,000 units of product. A comparison of standard and actual costs for the period on a total cost basis is also given above. There was no inventory of materials on hand to start the period. During the period, 21,000 metres of materials was purchased and used in production. The denominator level of activity for the period was 11,200 hours. Required: 1. For direct materials: a. Compute the price and quantity variances for the period. (Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).) Answer is not complete. Price variance Quantity variance b. Prepare journal entries to record all activity relating to direct materials for the period. Answer is not complete. General Journal Debit Credit No A Event 1 Raw materials Materials price variance Accounts payable 2. For direct labour: a. Compute the rate and efficiency variances. (Indicate the effect of variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).) Labour rate variance Labour efficiency variance Answer is not complete. U F b. Prepare a journal entry to record the incurrence of direct labour cost for the period. (List debit entries first). Answer is not complete. No Event General Journal Debit Credit 1 1 Work in process Labour rate variance Labour efficiency variance Wages payable

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter5: Process Costing
Section: Chapter Questions
Problem 2PB: The following product costs are available for Kellee Company on the production of eyeglass frames:...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Only typed solution 

Haliburton Mills Inc. is a large producer of men's and women's clothing. The company uses standard costs for all of its products. The
standard costs and actual costs for a recent period are given below for one of the company's product lines (per unit of product):
Standard Actual
Cost
Cost
Direct materials:
Standard: 4.0 metres at $4.60 per metre
Actual: 4.2 metres at $4.40 per metre
Direct labour:
$18.40
$18.48
Standard: 2.4 hours at $4.50 per hour
Actual: 2.2 hours at $4.85 per hour
10.80
10.67
Variable manufacturing overhead:
Standard: 2.4 hours at $2.20 per hour
Actual: 2.2 hours at $2.55 per hour
5.28
5.61
Fixed manufacturing overhead:
Standard: 2.4 hours at $3.80 per hour
Actual: 2.2 hours at $3.85 per hour
Total cost per unit
9.12
8.47
$43.60 $43.23
Actual costs: 5,000 units at $43.23
Standard costs: 5,000 units at $43.60
Difference in cost-favourable
$216,150
218,000
$ 1,850
During this period, the company produced 5,000 units of product. A comparison of standard and actual costs for the period on a total
cost basis is also given above.
There was no inventory of materials on hand to start the period. During the period, 21,000 metres of materials was purchased and
used in production. The denominator level of activity for the period was 11,200 hours.
Required:
1. For direct materials:
a. Compute the price and quantity variances for the period. (Indicate the effect of each variance by selecting "F" for favourable, "U"
for unfavourable, and "None" for no effect (i.e., zero variance).)
Answer is not complete.
Price variance
Quantity variance
b. Prepare journal entries to record all activity relating to direct materials for the period.
Answer is not complete.
General Journal
Debit
Credit
No
Event
A
1
Raw materials
Materials price variance
Accounts payable
2. For direct labour:
a. Compute the rate and efficiency variances. (Indicate the effect of variance by selecting "F" for favourable, "U" for unfavourable,
and "None" for no effect (i.e., zero variance).)
Labour rate variance
Labour efficiency variance
Answer is not complete.
U
F
b. Prepare a journal entry to record the incurrence of direct labour cost for the period. (List debit entries first).
Answer is not complete.
No
Event
General Journal
Debit
Credit
1
1
Work in process
Labour rate variance
Labour efficiency variance
Wages payable
Transcribed Image Text:Haliburton Mills Inc. is a large producer of men's and women's clothing. The company uses standard costs for all of its products. The standard costs and actual costs for a recent period are given below for one of the company's product lines (per unit of product): Standard Actual Cost Cost Direct materials: Standard: 4.0 metres at $4.60 per metre Actual: 4.2 metres at $4.40 per metre Direct labour: $18.40 $18.48 Standard: 2.4 hours at $4.50 per hour Actual: 2.2 hours at $4.85 per hour 10.80 10.67 Variable manufacturing overhead: Standard: 2.4 hours at $2.20 per hour Actual: 2.2 hours at $2.55 per hour 5.28 5.61 Fixed manufacturing overhead: Standard: 2.4 hours at $3.80 per hour Actual: 2.2 hours at $3.85 per hour Total cost per unit 9.12 8.47 $43.60 $43.23 Actual costs: 5,000 units at $43.23 Standard costs: 5,000 units at $43.60 Difference in cost-favourable $216,150 218,000 $ 1,850 During this period, the company produced 5,000 units of product. A comparison of standard and actual costs for the period on a total cost basis is also given above. There was no inventory of materials on hand to start the period. During the period, 21,000 metres of materials was purchased and used in production. The denominator level of activity for the period was 11,200 hours. Required: 1. For direct materials: a. Compute the price and quantity variances for the period. (Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).) Answer is not complete. Price variance Quantity variance b. Prepare journal entries to record all activity relating to direct materials for the period. Answer is not complete. General Journal Debit Credit No Event A 1 Raw materials Materials price variance Accounts payable 2. For direct labour: a. Compute the rate and efficiency variances. (Indicate the effect of variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance).) Labour rate variance Labour efficiency variance Answer is not complete. U F b. Prepare a journal entry to record the incurrence of direct labour cost for the period. (List debit entries first). Answer is not complete. No Event General Journal Debit Credit 1 1 Work in process Labour rate variance Labour efficiency variance Wages payable
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning