Figure 1 shows the schematic diagram of a three phase radial transmission system. The ratings and reactance of various components are as shown, along with the nominal transformer rated line voltage. Convert the schematic into an equivalent per unit circuit by using a base of 250 MVA and voltage reference as 40 kV at Zone C. Subsequently, calculate the new per unit reactance for all zones and load current at the receiving busbar.

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter9: Unsymmetrical Faults
Section: Chapter Questions
Problem 9.1P
icon
Related questions
Question
QUESTION 1
Figure 1 shows the schematic diagram of a three phase radial transmission system. The
ratings and reactance of various components are as shown, along with the nominal
transformer rated line voltage. Convert the schematic into an equivalent per unit circuit
by using a base of 250 MVA and voltage reference as 40 kV at Zone C. Subsequently,
calculate the new per unit reactance for all zones and load current at the receiving busbar.
(Zone C)
VBnew =40 kV
(Zone A)
(Zone B)
Vs
Vg = 33 kV
GA
11 kV 132 kV
Lc
134 kV 35 kV
100 MW
0.8 p.f.
lagging
j50 2
TA
150 MVA
X= 10 %
TB
120 MVA
200 MVA
10.8 kV
X= 12 %
X= 12 %
Te
50 MVA
X= 15 %
11 kV
10 MW
0.85 pf.
lagging
(Zone D)
Figure 1
32 kVy 11 kV
Transcribed Image Text:QUESTION 1 Figure 1 shows the schematic diagram of a three phase radial transmission system. The ratings and reactance of various components are as shown, along with the nominal transformer rated line voltage. Convert the schematic into an equivalent per unit circuit by using a base of 250 MVA and voltage reference as 40 kV at Zone C. Subsequently, calculate the new per unit reactance for all zones and load current at the receiving busbar. (Zone C) VBnew =40 kV (Zone A) (Zone B) Vs Vg = 33 kV GA 11 kV 132 kV Lc 134 kV 35 kV 100 MW 0.8 p.f. lagging j50 2 TA 150 MVA X= 10 % TB 120 MVA 200 MVA 10.8 kV X= 12 % X= 12 % Te 50 MVA X= 15 % 11 kV 10 MW 0.85 pf. lagging (Zone D) Figure 1 32 kVy 11 kV
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 9 steps with 2 images

Blurred answer
Knowledge Booster
Compensation Techniques in Transmission Line
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning