Earned Value formulas. • SV = EV - PV; SPI = EV/PV • CV = EV - AC; CPI = EV/AC • CR = SPI x CPI Prob. 1. Find the schedule variance(SV) and cost variance (CV) for a project underway that has an actual cost (AC) of $540,000, a scheduled cost (PV) of $523,000, and an earned value (EV) of $535,000. Prob. 2. A project in progress had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the spending (cost) and schedule variances and the CPI and the SPI. What is the Critical Ratio (CPI times SPI)? Prob. 3. A construction project underway exhibits an actual cost of $78,000, and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000. What are the spending and schedule variances? What is the critical ratio?

Essentials of Business Analytics (MindTap Course List)
2nd Edition
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Chapter15: Decision Analysis
Section: Chapter Questions
Problem 24P: Translate the following monetary payoffs into utilities for a decision maker whose utility function...
icon
Related questions
Question
Earned Value formulas.
• SV = EV - PV; SPI = EV/PV
• CV = EV - AC; CPI = EV/AC
CR = SPI x CPI
Prob. 1. Find the schedule variance(SV) and cost variance (CV) for a project underway that has an actual cost (AC) of $540,000, a scheduled cost (PV) of $523,000, and an
earned value (EV) of $535,000.
Prob. 2. A project in progress had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the spending (cost) and schedule variances
and the CPI and the SPI. What is the Critical Ratio (CPI times SPI)?
Prob. 3. A construction project underway exhibits an actual cost of $78,000, and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000. What
are the spending and schedule variances? What is the critical ratio?
Transcribed Image Text:Earned Value formulas. • SV = EV - PV; SPI = EV/PV • CV = EV - AC; CPI = EV/AC CR = SPI x CPI Prob. 1. Find the schedule variance(SV) and cost variance (CV) for a project underway that has an actual cost (AC) of $540,000, a scheduled cost (PV) of $523,000, and an earned value (EV) of $535,000. Prob. 2. A project in progress had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the spending (cost) and schedule variances and the CPI and the SPI. What is the Critical Ratio (CPI times SPI)? Prob. 3. A construction project underway exhibits an actual cost of $78,000, and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000. What are the spending and schedule variances? What is the critical ratio?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning