1.
How many increments have been identified for the M1235 Medium Light Tactical Truck (MLTT)?
Three
Feedback:
Correct!
2.
What is the name of the current prime contractor for the M1235 Medium Light Tactical Truck (MLTT)?
Kenosha Truck Manufacturing (KTM)
Feedback:
Correct!
3.
Which one of the following improvements is NOT included in the M1235A2 increment?
Engine Upgrade
Feedback:
Correct!
4.
Fill in the blank with the correct answer: "The current time (time now) in the PMT 2570 Scenario is:___________."
May 2012
Feedback:
Correct!
5.
Which one of the following is NOT a typical key consideration when selecting members for an Integrated Product Team (IPT)?
How recently the member completed a team building training course
Feedback:
Correct!
6.
Agreed upon guidelines or norms for individual and team behavior that describe how the team members will interact with one another, what processes they will use, and what they expect of one another, are examples of which one of the following?
Operating agreements
Feedback:
Correct!
7.
Before beginning to generate potential alternatives to resolve an issue or problem, you should first do which ONE of the following?
Investigate the issue and determine the objectives
Feedback:
Correct!
8.
Which ONE of the following artifacts displays and defines the product, or products, to be developed and/or produced and relates the elements of work to be accomplished to each other and to the end product?
Work Breakdown Structure (WBS)
Feedback:
Correct!
9.
What are the TWO types of Work Breakdown Structures (WBSs) used in the Department of Defense (DoD)?
Program WBS and Contract WBS
Feedback:
Correct!
10.
Which ONE of the following is the end result of the second step (Sequence the Tasks) in the scheduling process?
A network diagram reflecting the sequence of tasks and their relationships to one another
Feedback:
Correct!
11.
Fill in the blanks with the correct answer: "The event-based _____________ is expanded in the time-based ______________ to show all the detailed tasks required to accomplish the work effort."
Integrated Master Plan (IMP); Integrated Master Schedule (IMS)
Feedback:
Correct!
12.
Fill in the blank with the correct answer: "The longest path through the schedule network (the path with the greatest sum of task time durations) is known as the ____________________."
critical path
Feedback:
Correct!
13.
Fill in the blank with the correct answer: "An analogous cost estimate is one that uses: ______________________."
an evaluation of the differences between the new system and historical information for similar systems completed in the past
Feedback:
Correct!
14.
The contractor’s DIRECT costs normally consist of which ONE of the following?
Direct labor, direct materials, and other direct costs
Feedback:
Correct!
15.
A risk is identified by which ONE of the following choices?
The probability (greater than 0, less than 1) of an undesired event or condition and the consequences, impact, or severity of the undesired event, were it to occur
Feedback:
Correct!
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
16.
Which one of the following is NOT true concerning risk identification?
Is conducted only one time during the acquisition process
Feedback:
Correct!
17.
Fill in the blank with the correct answer: "The FOUR common risk mitigation strategies used in DoD are:________________."
Accept, avoid, transfer, and control
Feedback:
Correct!
18.
Which ONE of the following tools is useful in identifying product teams?
Work Breakdown Structure (WBS)
Feedback:
Correct!
19.
The use of Technology Readiness Levels (TRLs) enables consistent, uniform, discussions of technical maturity across different types of technologies. The levels span the earliest stages of scientific investigation (TRL 1) to the successful use in a system (TRL 9). What is the definition of TRL 6?
System/subsystem model or prototype demonstration in a relevant environment
Feedback:
Correct!
20.
When using the 14-Point Schedule Metrics (formerly DCMA 14-Point Schedule Metrics), incomplete tasks which have a baseline duration greater than 44 working days (2 months), and a
baseline start date within the detail planning period or rolling wave fall under the following metric:
High Duration
Feedback:
Correct!