Q: Draw the allocation of resources chart
on the earliest and latest start time for the
project that its information shown below,
and identify the most reasonable of them
and why?
D EFG
Activities
A
K
Events
1-2
1-3 2-4
2-5
3-4
4-7
4-8
5-6
6-9
7-9
8-9
Duration
5
4
3
2
1
4
resources
3
5
4
2
6
1 Add file
6.
5. Give 5 components of a Project Management Information System.
6. Give 4 key types of estimates.
Using the same CPM diagram, what is the total project duration?
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
C
10 weeks
D
C
6 weeks
4 weeks
5 weeks
7 weeks
9 weeks
7 weeks
8 weeks
4 weeks
E
C
F
E
G
D
E, G
Do the electrical work
F, I
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
K
5 weeks
M
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
Knowledge Booster
Similar questions
- A. Create the Network Diagram for the project . B . Identify the critical path and the minimum duration to complete the whole project ? C . Assume that it took 5 weeks to choose an architect , what is the effect on project completion date ? D. Draw Gantt chart .arrow_forwardThe is a schedule forecast of the probable duration of a project.arrow_forwardWhich type of information can be added to BIM? All the answers are correct Schedule Cost Specificationsarrow_forward
- Q#: Differentiate between rough and detailed cost estimate with examples.arrow_forwardQ# Discuss about stakeholders of Construction projectarrow_forwardThere are many procedures in Quality Management. Give an example procedure in construction to achieve the quality objectives of the project. Write a short essay/reaction on the given procedure.arrow_forward
- Describe the project delivery method?arrow_forwardThe contractor implements last planner on the project. During week 1, the following tasks are planned and committed by different subcontractors. At the end of week 1, the status of the tasks is also shown in the following table. What is the percent plan complete (PPC) for week 1? Explain what PPC measures? Committed on Completion Progress Completion? Mobilize Yes 100% Yes Install Security Fence Yes 100% Yes Set Forms Yes 80% No Excavate Planter Foundation Yes 100% Yes Construct Masonry Planter Yes 50% Noarrow_forwardProject closeout is the final construction phase of the project lifecycle. This phase occurs after physical construction has been completed, but before the project is actually turned over to the owner. Identify and discuss the activities necessary to ensure a smooth project close out. Give appropriate examples such as charts or diagrams.arrow_forward
- 4. Project managers have many resources that are not directly under their control, such as the designer and the owner. Provide at least 5 bulleted points describing in detail how project managers can manage (influence) resources outside of their control or above them in the contractual hierarchy. 5. For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and calculate the project duration. Then draw a time-scaled network and under it a labor resource histogram for the ES. Do the same for the LS. In both cases, use the maximum allowable number of workers. Make adjustments to the noncritical activities, within the constraints of the ES and LF and the maximum and minimum workers allowed to provide what you feel is the best labor distribution. Please use Table B (Table B.pdf) Lastly, Explain in detail what do you feel is the biggest problem with the ES and LS configurations, and how has…arrow_forwardOutline probable cost component and all possible consideration to establish budget proposal for a typical project and relate in practice methods/combination of charges for engineering services (select type of project).arrow_forwardDraw manually a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning