Sustainable Energy
2nd Edition
ISBN: 9781337551663
Author: DUNLAP, Richard A.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
Pls answer thank you!
At a proposed hydroelectric plant site, the average elevation of headwater is 600 m, the tailwater elevation is 480 m. The average annual water flow is determined to be equal to the volume flowing through a rectangular channel 4 m wide and 0.5 m deep and average velocity of 5.5 m/sec. Assuming that the plant site can develop if the hydraulic turbine that will be used has an efficiency of 80% and generator efficiency of 92%. Consider a headwork loss of 4% of the available head. Find the annual energy produce in kW.
Two reservoirs A and B have elevations of 250 m and 100 m, respectively. It is connected by a pipe having adiameter of 250 mm and a length of 100 m. A turbine, with an efficiency of 0.95, which is installed at a point inbetween A and B, is used to supply 233 kW of electric power to a nearby community. If the total head loss as watertravelled from reservoir A to B is 25 m, determine the discharge inside the pipe in liters per second.
Q110. A hydropower plant has to work under the
following conditions. Determine the likely
number of turbines of specific speed 120 for
the plant.
Net head = 20 m
Speed = 300 r.p.m
Discharge
= 6 m/sec
Hydraulic efficiency 97%
%3D
Volumetric efficiency 98%
%3D
Mechanical efficiency 92%.
%3D
Knowledge Booster
Similar questions
- Water flows through a 7.5 m diameter penstock on a dam at a flow rate of 113 m3/s. The total head available for the turbine is 18.4 m. The specifiic weight of water is 9810 N/m3. What is the power generated by the turbine?arrow_forwardA new 144 MW hydropower station is to be built at a site where the available head is estimated at 270 m. The generators require the turbine to rotate at 10 rad/sec. The only available turbines are Francis turbines with KN (the non-dimensional parameter to classify turbine ) equal to 0.08. Determine the number of turbines required.arrow_forwardQUESTION 3 Water must flow over a distance of 2 800 m from a large catchment dam to a turbine. The water level in the catchment dam is 1 620 m above sea level and the turbine is situated 1 275 m above sea level. The efficiency of transmission is 65% and 300 kW must be transmitted from the pipeline to the turbine. If f 0.007, determine the number of 200 mm diameter pipelines, which must be laid in parallel, needed to transmit the required power.arrow_forward
- During a prefeasibility survey, you have identified a feasible site for a micro hydropower scheme. If you’ve measured a gross head of 40 m, and from the hydrological analysis, a design flow of 150 l/s appears to be available throughout the year, what would be the likely installed capacity? Assume an overall efficiency of 60%.arrow_forwardDetermine the total energy production of a run-of-river plant having an total efficiency of 85%. It receives flow by means of a penstock, 400m long with 1.2m diameter, and f=0.015 in Darcy-Weisbach equation. The available head is 200m and seasonal fluctuations of upstream and downstream water levels are ignored. The flow duration data are tabulated as below.arrow_forwardAt a proposed hydroelectric power plant site, the average elevation of headwater is 600m and the tailwater elevation is 480m. The average annual water flow is determined to be equal to that volume flowing through a rectangular channel 4m wide and 0.5m deep and average velocity of 5.5m/s. Assuming the plant will operate 350 days/year, find the energy kwh that the plant site can developed if the hydraulic turbine that will be used has an efficiency of 78% and generator efficiency of 90%. Consider a headwork loss of 4% of the available head.arrow_forward
- Water discharging into a 10 m wide rectangular horizontal channel from a sluice gate is observed to have undergone a hydraulic jump. The flow depth and velocity during the jump are 0.8 m and 7 m/s respectively. The wasted power production potential due to the hydraulic jump is kW. (round off to two decimal places)arrow_forwardWater is pumped 14.5 km from a reservoir at elevation 30 m to another reservoirat elevation 70 m. The steel pipeline connecting the reservoirs has a nominal diameter of 1400mm (the actual inside diameter is 1372 mm) with C = 90. If the flow is 1.18 m3/s, the pumpingefficiency is 82%, and electricity costs $0.14/kWh. Assuming that the density of water is 1000kg/m3, what will be the monthly power bill? Sketch the hydraulic and energy grade lines.arrow_forward25 Which of the following power plant is an example of Tidal energy? a. Onshore system b. offshore System c. Salter Duck System d. None of thesearrow_forward
- A rectangular channel 2.0 m wide and 1.0 m deep carries a discharge of 4.0 m3/s. A horizontal datum is assumed 2.0 m below the channel bed at a certain point. Calculate the total energy and the specific energy at that pointarrow_forward2.1 A hydro-electric power station has a reservoir area of 2.7 km² and a capacity of 4.6 x 106m³. The effective head of water is 100 metres. The penstock, turbine and generation efficiencies are 95%, 90%, and 85%, respectively. Instructions :round off to 2 decimal places 1. Determine the total electrical energy that can be generated from the power station (kWh). 2. Determine the depth of the reservoir (metres) 3.Determine the fall in reservoir volume level is the load of 100 kW is supplied for 5 hours (%).arrow_forwardA- Two velocity components are given in the following case, find the third components such that it satisfies the continuity equation? u = x' + y +2, v= - x'y - yz - x B- Draw the energy lines between points A to B for the flow shown in figure (4) and demonstrate their components? Reservoir 1 Reservoir 2 Pipe Figure (4)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you