Zeke's Bikes uses a standard cost system and provides the following information: Standards: Static budget variable overhead $5,040.00. Static budget fixed overhead $20,900.00. Static budget direct labor hours 400 hours. Static budget number of units 25,600 units. Static budget direct labor hours 0.035 hours per unit.   Actual: Number of units produced 25,000. Actual variable overhead $5,220.00 Actual fixed overhead $23,600.00. Actual direct labor hours 520.   (Round your answers to two decimal places when needed and use rounded answers for all future calculations). 1. Compute the variable and fixed overhead allocation rates.

Accounting
27th Edition
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Chapter22: Budgeting
Section: Chapter Questions
Problem 22.5DQ: Under what circumstances is a static budget appropriate?
icon
Related questions
Topic Video
Question

Zeke's Bikes uses a standard cost system and provides the following information:

Standards:

Static budget variable overhead $5,040.00.
Static budget fixed overhead $20,900.00.
Static budget direct labor hours 400 hours.
Static budget number of units 25,600 units.
Static budget direct labor hours 0.035 hours per unit.

 

Actual:

Number of units produced 25,000.
Actual variable overhead $5,220.00
Actual fixed overhead $23,600.00.
Actual direct labor hours 520.

 

(Round your answers to two decimal places when needed and use rounded answers for all future calculations).

1. Compute the variable and fixed overhead allocation rates.      

Budgeted VOH
5,040 ✓
Budgeted FOH
20,900✔
(AC
0.21 X
(AQ
25,000 X
2. Calculate the variable overhead cost and efficiency variances.
Act. FOH
?
23,600✔
?
?
?
?
Budgeted allocation base = Standard VOH allocation rate
25,600 X
0.20 X
Budgeted allocation base = Standard FOH allocation rate
25,600 X
-0.82 X
SC)
SQ)
0.20 x
25,600 X
XV
?
3. Calculate the variable overhead cost variance.
?
Xv
=
AQ
25,000 X
SC
0.20 X
=
=
=
Variable OH Cost
Variance
-250 X
Variable Overhead
Efficiency Variance
120 X
Favorable or
Unfavorable
Unfavorable ✓
Favorable
Favorable or
Unfavorable
Favorable
Budget FOH = Fixed OH Cost Variance Favorable or Unfavorable
20,900✓ = 2,700.00✓
Transcribed Image Text:Budgeted VOH 5,040 ✓ Budgeted FOH 20,900✔ (AC 0.21 X (AQ 25,000 X 2. Calculate the variable overhead cost and efficiency variances. Act. FOH ? 23,600✔ ? ? ? ? Budgeted allocation base = Standard VOH allocation rate 25,600 X 0.20 X Budgeted allocation base = Standard FOH allocation rate 25,600 X -0.82 X SC) SQ) 0.20 x 25,600 X XV ? 3. Calculate the variable overhead cost variance. ? Xv = AQ 25,000 X SC 0.20 X = = = Variable OH Cost Variance -250 X Variable Overhead Efficiency Variance 120 X Favorable or Unfavorable Unfavorable ✓ Favorable Favorable or Unfavorable Favorable Budget FOH = Fixed OH Cost Variance Favorable or Unfavorable 20,900✓ = 2,700.00✓
Expert Solution
steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,