You're a construction engineer and one of your responsibilities is to estimate and schedule construction workers to complete projects. You've been given the job to frame a house and you know that 20 workers can complete the job in 12 days if the number of working hours per day is 8. However, you only have a construction crew of 17 workers and your contract requires that you complete the framing in 8 days. If the job is to be completed in 8 days with 17 workers, what will be the working hours per day?
Round your answer to the nearest tenth of an hour.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.Similar questions
- Use simplex methodarrow_forwardTaylor is paid on the frst day of the month and $80 is automatically deducted from her pay and deposited in a savings account. If the account pays 2.5% interest compounded monthly, how much will be in the account after 3 years and 9 months?arrow_forwardThis is the semester that you will take your required psychology and social science Because you decide to register early, there are 10 sections of psychology and from which to choose. Furthermore, there are 4 sections of social science that are available at times that do not conflict with those for psychology. In how many ways can you create two-course schedules that satisfy the psychology-social science requirement?arrow_forward
- The Walters Manufacturing Company needs to know how best to use the time available within its three manufacturing departments in the construction and packaging of the three types of metal storage sheds. Each one must be stamped, painted, and packaged. Table below shows the number of hours required for the processing of each type of shed. Using the information in the table, determine how many of each type of shed can be produced if the stamping department has 3200 hours available, the painting department has 1700 hours, and the packaging department has 1300 hours. Shed Department Type I Турe II Турe III Stamping 4 Painting Packaging 2. 2.arrow_forwardA rectangle field is to be watered by a rotating sprinkler head with a range of 25 feet. The sprinkler is to be placed in the middle of the field and the water set to just reach the corners of the field. If the area of the field is 1000 square feet, what are the dimensions of the field?arrow_forwardAn air traffic controller is monitoring two small planes flying at the same altitude. One isflying towards the control tower from the West at 120 miles per hour and is currently 5 milesaway from the tower. The other plane is now on top of the tower and flying South at 150miles per hour. In order to respect local safety rules the planes have to be always more than4 miles from each other, or fly at different altitudes. Should the controller order one of theplanes to change altitude, or will they always be farther than 4 miles from each other?arrow_forward
- In a medical supply room, there are 165 packages of type O positive blood and 210 packages of type AB negative blood. It is important not to confuse these two types of blood. If we want to stack piles of each type of blood on a shelf, with only one type of blood in a pile, what is the largest number of packets of blood that we can have in each pile if each pile is of the same size?arrow_forwardOne of the worst movies ever made was a film called Waterworld. The film was set in a future world in which ice caps have melted and water covers the Earth. Kevin Costner stars as The Mariner, a mutant who can breathe under water. His job is to protect a young girl who has what may be a map of dry land tattooed on her back; an evil gang riding Jet Skis is trying to kidnap her to get the map. The first thing the film’s producers did was pay Kevin Costner $14 million to star in the film. Then they started actual filming, and things went wrong very quickly. The movie was filmed almost entirely on and under water – many in the crew became seasick each day, much of the camera equipment did not work well under water, and scenes were taking much longer than expected to shoot. A series of accidents added to the costs and further delayed production. After 6 months of filming, the movie was not quite complete. Producers of the film discussed whether they should just stop everything and walk…arrow_forwardRoberto is the owner of the “Arrachera Queen” taco shop, which sells flank steak tacos, mmmm delicious! It is the most famous taqueria in Atizapán de Zarogoza, although its business is not a monopoly, its demand per hour makes it become one. In the surroundings there are other taquerías, but they are completely empty. His business, on Fridays (from seven at night), becomes a real madness. Faced with such a situation, Roberto would like to influence the price of the tacos to try to relieve the people of his premises, which also brings him problems with the Municipality due to the large number of cars that are parked up to triple row to get at least an order of tacos. On weekends it is even worse, because too many people come to his place. Suddenly Roberto finds out that you (one of his spoiled clients) have taken a course in Economics for Business Creation, so he asks for your help to find out what the optimal benefit is: Roberto tells him that the price per taco is p=12−1/12Q Whereas…arrow_forward
- A chef purchases whole chickens because they cost less per pound than fabricated cuts and the carcasses can be used to make stock for soup. If the soup consists of 9 parts chicken stock, 2 parts chicken, 1.5 parts vegetables and 1.5 parts noodles, all by weight, how much of each ingredient is needed to make 2 gallons of soup?arrow_forwardif 12 machines take 24 days to complete a job, how long will it take for 39 machines to do the job?arrow_forwardMalcom runs a store selling custom made computers in only 2 hours. His new assistant, Jamal, is less experienced and requires 3 hours to assemble each computer. Working together, how long will it take Malcolm and Jamal to clear their backlog of 70 ordersarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Advanced Engineering MathematicsAdvanced MathISBN:9780470458365Author:Erwin KreyszigPublisher:Wiley, John & Sons, IncorporatedNumerical Methods for EngineersAdvanced MathISBN:9780073397924Author:Steven C. Chapra Dr., Raymond P. CanalePublisher:McGraw-Hill EducationIntroductory Mathematics for Engineering Applicat...Advanced MathISBN:9781118141809Author:Nathan KlingbeilPublisher:WILEY
- Mathematics For Machine TechnologyAdvanced MathISBN:9781337798310Author:Peterson, John.Publisher:Cengage Learning,
Advanced Engineering Mathematics
Advanced Math
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Advanced Math
ISBN:9780073397924
Author:Steven C. Chapra Dr., Raymond P. Canale
Publisher:McGraw-Hill Education
Introductory Mathematics for Engineering Applicat...
Advanced Math
ISBN:9781118141809
Author:Nathan Klingbeil
Publisher:WILEY
Mathematics For Machine Technology
Advanced Math
ISBN:9781337798310
Author:Peterson, John.
Publisher:Cengage Learning,