You have a project to build a new fence. The fence is four sided as shown below. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three. Answer the questions below using this project status chart: Activity Side 1 Side 2 Side 3 Side 4 Key: S = Actual Start F = Actual Finish PS= Planned Start PF = Planned Finish A $480 B $4480 Day 1 -$480 S ---------- F $1680 Day 2 S ------ -PF Day 3 F PS---S---PF Day 4 PS-------PF Status End of Day 3 Complete, spent $1,000 If this project is handled at the same cost performance as present, how much more will this project cost since the end of the third day? Complete, spent $1,200 50% done, spent $600 Not yet started

EBK ELECTRICAL WIRING RESIDENTIAL
19th Edition
ISBN:9781337516549
Author:Simmons
Publisher:Simmons
Chapter28: Overcurrent Protection–fuses And Circuit Breakers
Section: Chapter Questions
Problem 13R: All electrical components have some sort of withstand rating. The NEC and UL Standards refer to this...
icon
Related questions
Question
You have a project to build a new fence. The fence is four sided as shown below. Each side is to take one day to build and is
budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three.
Answer the questions below using this project status chart:
Activity
Side 1
Side 2
Side 3
Side 4
Key:
S = Actual Start
F = Actual Finish
PS= Planned Start
PF = Planned Finish
A $480
B $4480
Day 1
-$480
S ---------- F
$1680
Day 2
S ------ -PF
Day 3
F
PS---S---PF
Day 4
PS-------PF
Status End of
Day 3
Complete,
spent $1,000
If this project is handled at the same cost performance as present, how much more will this project cost since the end of
the third day?
Complete,
spent $1,200
50% done,
spent $600
Not yet started
Transcribed Image Text:You have a project to build a new fence. The fence is four sided as shown below. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three. Answer the questions below using this project status chart: Activity Side 1 Side 2 Side 3 Side 4 Key: S = Actual Start F = Actual Finish PS= Planned Start PF = Planned Finish A $480 B $4480 Day 1 -$480 S ---------- F $1680 Day 2 S ------ -PF Day 3 F PS---S---PF Day 4 PS-------PF Status End of Day 3 Complete, spent $1,000 If this project is handled at the same cost performance as present, how much more will this project cost since the end of the third day? Complete, spent $1,200 50% done, spent $600 Not yet started
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
steps

Unlock instant AI solutions

Tap the button
to generate a solution

Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK ELECTRICAL WIRING RESIDENTIAL
EBK ELECTRICAL WIRING RESIDENTIAL
Electrical Engineering
ISBN:
9781337516549
Author:
Simmons
Publisher:
CENGAGE LEARNING - CONSIGNMENT