Question
What is the NPV of a project that costs $14,000 today and another $6,000 in one year, and is then expected to generate 12 annual cash inflows of $2,000 starting at the end of year 5. Cost of capital is 9%. Round to the nearest cent. [Hint: There are two outflows here, today and year 1. You will need to discount the year 1 cost at the project's discount rate when calculating PV(outflows).]
Numeric Answer:
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 4 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- A project that provides annual cash flows of $16,900 for eight years costs $75,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)arrow_forwardWhat is the discounted payback of a project that has an initial outlay of $20,000 and will generate $6,000 in year 1, $12,000 in year 2, $9,000 in year 3, and $14,000 in year 4 assuming the cost of capital is 10%?arrow_forwardYou are considering investing in a project that has an initial cost of $10,000, a WACC of 10%, with the estimated net cashflows for years 1, 2, 3 being equal to $4000, $ 9,000, $21,000. What is the project’s NPV?arrow_forward
- Suppose an investment has an initial capital cost of $1100, an ongoing cost of $6.50 per year and an annual benefit of $80. If the project lasts for 20 years and the discount rate is 7%, the internal rate of return is: Provide your answer in percentage form (e.g. an IRR of 17.66% should be entered as 17.66) to 2 decimal places. Do not include any $ or % 's in your response.arrow_forwardA project that provides annual cash flows of $16,900 for eight years costs $75,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)arrow_forwardA project will have an initial investment requirement of $5,000. Then, it will generate 5 years of $1,000 per year, with all cash expected to be received at the end of the year. The discount rate is 10%. The hurdle rate is the same as the discount rate, 10%. 9.What is the NPV? 10.What is the Payback? 11.What is the IRR. 12.Do you accept this project? 13.At WHAT HURDLE RATE would the project result in an NPV of exactly $0?arrow_forward
- Perform a financial analysis for a project. Assume that the projected costs and benefits for this project are spread over 6 years as follows. Estimated costs are $1,100,000 in Year 0, and $50,000 each year in Years 1, 2, 3, 4, 5 and 6. Estimated benefits are $0 in Year 0, and $450,000 each year in Years 1, 2, 3, 4, 5 and 6. Use a 15% discount rate. Suppose the required payback period and discounted payback period are both 3 years. (1) Calculate the payback period (based on the original cash flows without discounting), and evaluate the project based on the payback method. (2) Calculate the discounted payback period (based on discounted cash flows), and evaluate the project based on the discounted payback method. (3) Evaluate the project using the NPV method, and explain whether you would recommend investing in this project.arrow_forwardA project has an initial cost of $75,000, expected net cash inflows of $13,000 per year for 10 years, and a cost of capital of 10%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round intermediate calculations. Round your answer to the nearest cent.arrow_forwardFind internal rate of return of a project with an initial cost of $43,000, expected net cash inflows of $9,550 per year for 8 years, and a cost of capital of 10.50%.Round your answer to two decimal places. For example, if your answer is $345.667 round as 345.67 and if your answer is .05718 or 5.718% round as 5.72. Group of answer choices 15.05% 14.60% 14.90% 16.24% 17.73%arrow_forward
- An investment has an installed cost of $565,382. The cash flows over the four-year life of the investment are projected to be $194,584, $238,318, $186,674, and $154,313. If the discount rate is zero, what is the NPV? Note: Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32. If the discount rate is infinite, what is the NPV? Note: A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32. At what discount rate is the NPV just equal to zero? Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.arrow_forwardProject L requires an initial outlay at t = 0 of $40,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ ______arrow_forwardYou are trying to decide between the following two projects: Cash Flows ($ thousands) Project : Today One Year Later Two Years Later A -30 15 25 B -80 40 60 You can undertake only one project. (1) What is the IRR of each project? (2) If your cost of capital is 5%, which project should you undertake?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Essentials Of InvestmentsFinanceISBN:9781260013924Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.Publisher:Mcgraw-hill Education,
- Foundations Of FinanceFinanceISBN:9780134897264Author:KEOWN, Arthur J., Martin, John D., PETTY, J. WilliamPublisher:Pearson,Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage LearningCorporate Finance (The Mcgraw-hill/Irwin Series i...FinanceISBN:9780077861759Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan ProfessorPublisher:McGraw-Hill Education
Essentials Of Investments
Finance
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Mcgraw-hill Education,
Foundations Of Finance
Finance
ISBN:9780134897264
Author:KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:Pearson,
Fundamentals of Financial Management (MindTap Cou...
Finance
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i...
Finance
ISBN:9780077861759
Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:McGraw-Hill Education