What is the critical path and duration for this project?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
  1. What is the critical path and duration for this project?

 

Activity / Task
A
B
с
D
E
LL
F
G
Dependency
Start
Follow A
Follow A
Follow B & C
Follow C
Follow D & E
Follow F
Dependency Type
Mandatory
Discretionary
Mandatory
Discretionary
Mandatory
Mandatory
Effort per person
per day
(Mandays)
1
4
6
4
6
4
2
Duration (Days)
1
2
3
2
3
4
2
Transcribed Image Text:Activity / Task A B с D E LL F G Dependency Start Follow A Follow A Follow B & C Follow C Follow D & E Follow F Dependency Type Mandatory Discretionary Mandatory Discretionary Mandatory Mandatory Effort per person per day (Mandays) 1 4 6 4 6 4 2 Duration (Days) 1 2 3 2 3 4 2
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.