FROM THE TEXT (Project Management): The project team decides the work that will be self-performed—performed by members of the project team—and the work that will be outsourced to others. The procurement strategy focuses on the work that will be outsourced—performed by outsiders.
Luu, Ng, and Chen (Luu, Ng, & Chen, 2003) studied project procurement selection priorities and identified budget and
Outsourcing Steel and Concrete in New York
A construction company has a contract to build a large building in downtown New York. Most, if not all, the construction materials, such as steel and concrete, will be purchased from companies that specialize in steel and concrete. Existing companies that produce and sell steel can provide the steel the project needs at a much lower cost and faster than if the project manager’s organization attempted to build the capacity itself.
Some outsourcing decisions—sometimes called make or buy decisions—are more difficult. On the same building construction project, new construction materials and methods are required that will make the building more energy efficient. The project manager can outsource this portion of the project to companies that have this expertise or develop this expertise on the project and self-perform the work. The costs of developing this expertise within the project will be more expensive and may take more time than outsourcing this work.
Self-performing this work also has benefits. The project team would develop this expertise and the additional expertise would add value to the parent company and save money on future projects. The project management team would have greater control over the work because the work would be performed by members of the project team instead of outsiders. Self-performing and outsourcing the work have both benefits and risks.
This decision is primarily influenced by the following:
- Cost (budget)
- Schedule
The following factors also influence outsourcing decisions:
- Risk
- Quality
- Flexibility
Outsourcing Versus Self-Performing
On the New York building construction project, the project manager decided to outsource the portion of the work that required new methods and materials. The project team assigned engineers from the project team to evaluate the work during the project and to assess the appropriate methods and costs for the parent company to develop this capacity within the company. The additional costs of developing the capacity and the additional risks of implementing a new method with existing resources outweighed the benefits of developing the capacity within the organization.
The project procurement strategy begins with these self-perform or buy decisions.
New York Construction Project
On the New York building construction project, the basic engineering and construction activities are core expertise of the parent company, and the project team had access to the qualified resources to perform the work. The decision to self-perform this portion of the work was easy because the company had a cost and schedule advantage by using the existing resources. The purchase of the steel, concrete, and other commodities was also easy because the costs of developing those resources far outweighed the benefit of purchasing them.
Some of the procurement decisions are not so obvious and the project team evaluates the cost, schedule, quality, flexibility, and risk implication of self-performing versus outsourcing the work.
Key Takeaways
- The factors that influence procurement are primarily cost and schedule but also include risk, quality, and flexibility.
- To determine whether to outsource or do the work within the organization, consider which option is less costly and which option can deliver the work on time.
QUESTION TO ANSWER:
What is one advantage of doing the work within the organization instead of outsourcing it?
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
- This assignment is a continuation from the Case Study Sign-Up where you will do research on market intelligence, competitive intelligence and product intelligence to export a product/service to the market BWIT (Beauty World International Trading) for a Canadian exporter. Company's name: BWIT (Beauty World International Trading) Product/Service: The company offers a line of natural perfumes under the brand name "The 7 Virtues." The perfumes are made using essential oils from countries experiencing turmoil and strife, and a portion of the profits is donated to support the farmers in those regions. Link: https://www.international.gc.ca/world-monde/stories-histoires/2019/bwit-7-virtues-faci.aspx?lang=eng Markets mentioned in the article: United States, United Kingdom, Australia. BWIT (Beauty World International Trading) is a company that specializes in natural perfumes under the brand name "The 7 Virtues". The perfumes are made with essential oils sourced from countries that are going…arrow_forward4. Using a discounted rate of 12 percent, INITIAL COST NET CASH FLOW YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 PROJECT A (BROILER) K100,000 (20,000) 10,000 40.000 40.000 150.000 PROJECT B (LAYERS) K100,000 33,000 33,000 33,000 33,000 33,000 a. Determine the net present value of project A and B b. Calculate the IRR on mutually exclusive investment of project A and B. C. Which project must the farm undertake and why?arrow_forwardOffice Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity D. Activity C is connected to activity E. Activity D is…arrow_forward
- Identify 4 possible bugs that could be found in the online quote component of an airline ticketing system, and briefly describe the bug tracking steps that can be followed to fix and resolve the bugs using Jira project management and bug tracking toolarrow_forwardThe owner of Maxwell's Coffee and Cakes wants to start selling products that feature her coffee shop's logo. Her first product will be backpacks which she will sell for $137.44 each. She can buy the backpacks for $21.97 and have them customized for $10.92 apiece. There is a one-time set up charge of $1,525.15 for customization. In order for the project to go forward, she needs to show a $14,718.68 profit. How many backpacks will she have to sell in order for this project to be acceptable? Round to the nearest whole number.arrow_forwardEvaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk Managementarrow_forward
- Why is EVM not used more? Explain how it can manage budgets and evaluate project performance. How do you evaluate cost variation, schedule variance, cost performance index, and schedule performance index figures?arrow_forwardNorth American Free Trade Agreement (NAFTA), General Agreement on Tariff and Trade (GATT), U.S.-China Trade Relations Act, and EU and WTO efforts are considered to be _________________. a. Risk management b. Quality problems c. Innovating d. Economic Conditions e. None of the abovearrow_forwardThroughout the lifecycle of an IT/IS project, please define outsourcing and describe two benefits it offers to a business.arrow_forward
- Issue Log: Analyze all entries in the Issue Log from the perspective of a project manager and explain the recommended course of action, noting the impact of the issue on scope, planning communications, and resourcing.arrow_forwardThe ideal outcome of the planning process group is to complete a project successfully by delivering the agreed-upon project scope within time, cost, and quality constraints Select one: True False Initiating involves developing a project charter, which is part of the project ______ management knowledge area. Select one: a. scope b. risk c. communications d. integration Estimate activity resources output Select one: a. Activity list, activity attributes, milestone list, project management plan updates b. Project schedule network diagrams, project documents updates c. Activity resource requirements, resource breakdown structure, project documents updates d. Schedule management plan As time progresses, the scope of a project should become ... Select one: a. more clear and specific b. more vague c. more ambiguous d. more difficultarrow_forwardGive an explanation of how earned value management (EVM) may be used to keep expenses under control and monitor the overall effectiveness of a project, and then hypothesise as to why it is not utilised more often. How can one determine if the data for cost variation, schedule variance, cost performance index, and schedule performance index are healthy or unhealthy? What are some basic rules of thumb?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.