Transcribed Image Text:Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be
unavailable for at least two weeks so processing times were adjusted.
Customer job 1
Processing time
(days)
Due date (days)
6
Use the EDD rule and compute the start time, flow time, lateness, and tardiness for each job. Use minus sign to enter negative lateness values, if any. If your answer is zero, enter "0".
Sequence Start Time, days Flow Time, days Lateness, days
Tardiness, days
-Select-
-Select-
-Sclect.
-Select-
-Select-
UI
5
LI
TE
10
MA
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 2 images

Knowledge Booster
Similar questions
- Eight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forwardhomework - need helparrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. DURATION (HOURS REQUIRED) 14 7 2 JOB ABCDE DUE DATE (HOURS HENCE) 36 14 16 6 26 6 10 a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be D, B, C, E, A. b) What is the average completion (flow) time? The average completion (flow) time is 19.6 days (round your response to one decimal place). c) What is the average job lateness? The average job lateness is 0.6 days (round your response to one decimal place). d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal…arrow_forward
- What method uses more processing time and resources: preemptive or non-preemptive scheduling?arrow_forwardPlease do not give solution in image format thankuarrow_forwardAs the Cottrell Bicycle Co. of St. Louis completes plans for its new assembly line, it identifies 25 different tasksin the production process. VP of Operations Jonathan Cottrell now faces the job of balancing the line. He lists precedencesand provides time estimates for each step based on work-sampling techniques. His goal is to produce 1,000 bicycles perstandard 40-hour workweek.Balance this operation using the shortest operation time rule and compute the efficiency of the line.arrow_forward
- Activity Greet customer Take order Process order Print receipt Activity Time per Customer 5 seconds 25 seconds 1.5 minutes 30 seconds If the demand rate is 20 customers per hour, what are the flow rate (in customers per hour), utilization, and cycle time (in minutes per customer)?arrow_forwardNote:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardThe following jobs are waiting to be processed at a small machine center; JOB 10 20 30 40 50 days (round your response to one decimal place). DUE DATE 260 254 260 265 275 days (round your response to one decimal place). DURATION (DAYS) All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rule, the sequence of jobs should be 50, 20, 10, 30, 40 b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). 18 22 14 4 32arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.