This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G. c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: Activity A Slack Time

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Activity Immediate Predecessor(s) Time (days)
A
Pש Q ס ח ח
B
C
D
E
F
G
B
A, D
C
E, F
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are B-D-E-G
c) The project length for the leadership training program development project = 28 days.
d) Slack time for each of the activities is:
Activity
A
4
6
3
10
4
5
8
Slack Time
Transcribed Image Text:Activity Immediate Predecessor(s) Time (days) A Pש Q ס ח ח B C D E F G B A, D C E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: Activity A 4 6 3 10 4 5 8 Slack Time
Expert Solution
Step 1

First we start with finding the Early Start Time (ES), Early Finish Time (EF), Late Start Time (LS), Late Finish Time (LF) using forward and backward pass.

ES and EF is calculated using forward pass where we start with the first activity and then move to the next activities in the network. First Activity is A so its ES will be 0. Similarly B and C don't have a predecessor so their ES will be 0 too.

Next EF times for A, B and C is calculated by adding the time to the ES. For Example, Activity A takes 4 days, its ES is 0, so EF time for Activity A is 0+4= 4 days. Similarly as shown below in the table EF time is calculated for B and C by adding the time to the ES values.

Next we see that Activity D starts after Activity B, hence ES for Activity D will be the EF of Activity B as D can start only after B finishes. EF is calculated again by adding time to the ES value.

Activity E can start only after A and D. A ends (EF) at 4 whereas D ends (EF) at 16. So E can start(ES) only at 16. Its EF will be Time of 4 days added to the ES value of 16 as shown below in the table.

Similarly we do the entire forward pass and fill the ES and EF values as shown in the table below.

Activity Immediate Predecessor Time( days) ES EF LS LF Slack (days)
A - 4 0 4 12 16 12
B - 6 0 6 0 6 0
C - 3 0 3 12 15 12
D B 10 6 16 6 16 0
E A,D 4 16 20 16 20 0
F C 5 3 8 15 20 12
G E,F 8 20 28 20 28 0
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.