The higher levels of the work breakdown structure (WBS) represent increasing amounts of detail while the lower levels represent broad categories of activities. True or False
True
False
Duration is defined as the time from the beginning to the end of an activity. True or False
A common resource constraint is availability. True or False
Group of answer choices
True
False
The _____ schedule is a summary level schedule that encompasses the entire project scope.
Group of answer choices
original
milestone
procurement
master
conceptual
Which of the following is NOT true about a master schedule?
Group of answer choices
If the project is chosen, a master schedule is created.
It has major events and dates such as starting date, important events, and the completion date.
The master schedule is rarely part of a contract.
Changes to the schedule must be approved using a documented change process with approval by the project sponsor and client.
To execute the schedule, the major activities are broken down into smaller activities and resources are assigned to those activities.
The project work breakdown structure (WBS):
Group of answer choices
developed around the functions of the project facilitates the understanding of the amount of work required for each stage of the project.
represents a breakdown of the project into components that encompasses a part of the scope of the project.
size is directly related to the duration of each of the activities of the project.
represents increasing amounts of detail at its highest level while the lower levels represent broad categories.
is a hierarchical listing and grouping of the project activities required to produce the deliverables of the project.
Which of the following is true about a work breakdown structure (WBS)?
Group of answer choices
Developing a WBS begins by defining and developing lists of all activities needed to accomplish the work of the project.
The first draft of the WBS includes activities at the low-level.
The first draft of the WBS typically includes the minor activities required to accomplish the deliverables identified in the project scope of work.
The WBS is decomposed to the level that the client needs to control the project.
Typically, smaller and simpler projects require more detailed WBS.
A(n) _____ has no duration or resources, and is simply an indicator of an important point in the project.
Group of answer choices
node
milestone
inference
hierarchy
attribute
To consider the availability of team members, consultants, and key pieces of equipment, you can create a(n) _____ which indicates working days and days off for a group or individual.
Group of answer choices
resource calendar
project calendar
task calendar
hierarchical calendar
base calendar
The relationship between a predecessor activity and a successor activity is called a(n) _____.
Group of answer choices
series
pattern
dependency
association
aggregation
Activities that have predecessor-successor relationships occur _____.
Group of answer choices
sequentially
concurrently
intermittently
sporadically
suddenly
If activities must begin at the same time, they have a _____ relationship.
Group of answer choices
finish-finish
sequential
finish-start
periodic
start-start
Lead time is _____.
Group of answer choices
the amount of time that separates the finish of one activity and the beginning of the next activity
greater for concurrent activities that end at the same time
a sequence of activities where the first activity must end before the next activity can begin
the amount of time that the start of the next activity can overlap the finish of its predecessor
lesser for concurrent activities that begin at the same time
The Gantt chart _______________________.
Group of answer choices
is usually difficult to read and analyze.
is also called a PERT chart.
is used to indicate duration and relationships between project activities.
illustrates complex relationships well.
is a time-scaled graphic that represents each activity with connected straight line segments.
All of the following are techniques project managers can use to accelerate the project schedule, EXCEPT:
Group of answer choices
improving quality.
reassigning resources.
changing the scope.
adding additional resources.
using contingency resources
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Resource requirements plans based on each activity's earliest start time are said to be based on an: as-late-as-possible schedule as-needed schedule as-soon-as-possible schedule as-flexible-as-possible schedule optimistic schedulearrow_forwardHow long it will take for each activity on the network chart is all but one of the following. Estimated duration The elapsed time that will be required Equal to the early start O Expressed in the same time units - days, hours, months, yearsarrow_forwardUse the “A1_Excel_Template” Excel file to solve the questions below. Submit two files for this assignment: The completed word file (use this file to compile your solutions) with your answers including Excel screenshots. The Excel file with your answers. Specific Instructions: The “A1_Excel_Template” file contains the data sets on separate worksheets (tabs) labeled as “ Problem 1_DHL”, “Problem 2_Patients”, and so on. Use these datasets to complete problems below. Save the solved problems in A1_Excel_Template as A1_Last Name. For Instance, Use this word file to compile your answers. You need to take a screenshot of your Excel answers ( e.g., frequency table, bar chart, pie chart, .. etc.) and paste it under appropriate question in this word file. Save the A1_ word file as A1_Last Name. For Instance, A1_Kochan. Submit the excel file and this word file that contain your answers.arrow_forward
- As the Cottrell Bicycle Co. of St. Louis completes plans for its new assembly line, it identifies 25 different tasks in the production process. VP of Operations Jonathan Cottrell now faces the job of balancing the line. He lists precedences and provides time estimates for each step based on work- sampling techniques. His goal is to produce 1,000 bicycles per standard 40-hour workweek. Task Time (sec) Immediate Task Time (sec) Immediate Predecessors Predecessors K3 60 E3 109 F3 K4 24 K3 D6 53 F4 K9 27 K3 D7 72 F9, E2, E3 J1 66 K3 D8 78 E3, D6 J2 22 K3 - D9 37 D6 J3 3 C1 78 F7 G4 79 K4, K9 B3 72 D7, D8, D9, C1 G5 29 К9, 1 B5 108 C1 F3 32 12 B7 18 B3 F4 92 J2 A1 52 B5 F7 21 J3 A2 72 B5 F9 126 G4 A3 114 B7, A1, A2 E2 18 G5, F3 a) Balance this operation using shortest operation time rule and compute the efficiency of the line. b) Discuss how this balance could be improved. Is it possible to improve this balance to 100%? O Focus ASUS VivoBookarrow_forwardFor the network schedule shown below, which statement is true? a. This is an example of the Activity-on-Node (AON) method of network diagramming.b. Activity F can start without waiting for the completion of Activity B.c. Activity B can occur concurrently with Activity D.d. To simplify the network, Activities F and G can be combined without changing the logic.arrow_forwardThe man-hours requirement is typically at a peak during the O a. termination O b. execution O c. conceptualization O d. planning The management department at the university decides to add a new program in restaurant, hotel, and institutional management. As part of the development process they hold focus groups consisting of area business leaders, current and former students, and restaurant and hotel owners. These groups can be described as: O a. Clients. O b. Project leaders. c. Project workers. Od. Stakeholders. -15°C Cloudy phase of the project life cycle. Q Search E A Parrow_forward
- An updated schedule that shows the present status of the project is called the _____ schedule. Question 17 options: performance index master milestone general conceptual currentarrow_forwardwhen discussing processes related to Project Execution, the ISO 10006 stabdard splits this category into different project groups. Which of the following is not one of these subcategories? a. Human resource-related processes b. Procurement processes c. Time related processes d. risk-related processarrow_forward1. What is the cycle time? 2. What is the theoretical minimum number of workstations? 3. Which of the following statements is FALSE? a. All of the tasks A, B and C should be finished first before task F can be started. b.All of the tasks A through H should be finished first before task I can be started. c.Tasks A, B, and C can be started as soon as possible. d. All of the tasks B, E, C and F should be finished first before task H can be started.arrow_forward
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the LAST workstation are O a. All tasks O b. Gonly…arrow_forwardResponsibility for the overhead efficiency variance should be assigned to whoever is responsible for control of the activity base underlying the flexible budget. True Falsearrow_forwardAs the project manager, you're in charge of creating an ICS (Inventory Control and Management Information System). The three-dimensional model is ideal for system administration.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.