The following data pertain to Job 615.
$ 2,500
$ 3,500
Direct materials
Direct labor
Overhead
Setups
Parts inspected
Machine hours
Required:
1. Classify each of the three overhead activities as unit level, batch level, product level, or facility level.
2. Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product
cost of Job 615.
3. Assume Business Solutions uses activity-based costing. (a) Compute overhead activity rates. (b) Allocate overhead cost to Job 615.
(c) Compute total product cost of Job 615.
Required 1 Required 2 Required 3
Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total
product cost of Job 615. (Round "Overhead rate" to 2 decimal places.)
Department
Allocate overhead to Job 615 using plantwide rate
Plantwide
Overhead Rate
Machine Hours
Used
Job 615
SANT
Total product cost of Job 615
Job 615
W
$
0³
S
F2
23
2 setups
400 parts inspected
600 machine hours
Direct Materials
20
F3
E
D
Direct Labor
$
4
R
F
Overhead Allocated
< Required 1
LL
+
Overhead
%
OF LO
5
Product Cost
$
G
F5
T
0
Required 3 >
Prev
<6
1 of 4
MacBook Air
F6
7
Y
&
7
G H
Next >
F7
U
* 00
8
DII
F8
-
9
F9
JK
O
0
expand button
Transcribed Image Text:*** The following data pertain to Job 615. $ 2,500 $ 3,500 Direct materials Direct labor Overhead Setups Parts inspected Machine hours Required: 1. Classify each of the three overhead activities as unit level, batch level, product level, or facility level. 2. Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product cost of Job 615. 3. Assume Business Solutions uses activity-based costing. (a) Compute overhead activity rates. (b) Allocate overhead cost to Job 615. (c) Compute total product cost of Job 615. Required 1 Required 2 Required 3 Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product cost of Job 615. (Round "Overhead rate" to 2 decimal places.) Department Allocate overhead to Job 615 using plantwide rate Plantwide Overhead Rate Machine Hours Used Job 615 SANT Total product cost of Job 615 Job 615 W $ 0³ S F2 23 2 setups 400 parts inspected 600 machine hours Direct Materials 20 F3 E D Direct Labor $ 4 R F Overhead Allocated < Required 1 LL + Overhead % OF LO 5 Product Cost $ G F5 T 0 Required 3 > Prev <6 1 of 4 MacBook Air F6 7 Y & 7 G H Next > F7 U * 00 8 DII F8 - 9 F9 JK O 0
es
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey decides to analyze
overhead cost at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up
most of the company's overhead. Additional information about overhead follows.
Activity
Set up
Inspection
Utilities
Total
The following data pertain to Job 615.
Direct materials
Direct labor
Overhead
Setups
Parts inspected
Machine hours
2
Required 1
Budgeted Cost
$ 20,000
Required:
1. Classify each of the three overhead activities as unit level, batch level, product level, or facility level.
2. Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product
cost of Job 615.
Department
3. Assume Business Solutions uses activity-based costing. (a) Compute overhead activity rates. (b) Allocate overhead cost to Job 615.
(c) Compute total product cost of Job 615.
Job 615
7,500
10,000
$ 37,500
F2
Required 2
Job 615
Total product cost of Job 615
W
Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total
product cost of Job 615. (Round "Overhead rate" to 2 decimal places.)
Allocate overhead to Job 615 using plantwide rate
Machine Hours
Used
$
#
3
$ 2,500
$ 3,500
Plantwide
Overhead Rate
Direct Materials
20
F3
E
2 setups
400 parts inspected
600 machine hours
Required 3
S D
Budgeted Activity Usage
25 setups
5,000 parts inspected
5,000 machine hours (MH)
Direct Labor
4
F4
R
F
Overhead Allocated
Overhead
%
5
Product Cost
$
Ų
F5
T
G
0
Prev
<6
1 of 4
MacBook Air
F6
Y
&
7
H
Next >
F7
U
* 00
8
J
DII
F8
-
(
9
F9
K
-O
O
0
expand button
Transcribed Image Text:es After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey decides to analyze overhead cost at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of the company's overhead. Additional information about overhead follows. Activity Set up Inspection Utilities Total The following data pertain to Job 615. Direct materials Direct labor Overhead Setups Parts inspected Machine hours 2 Required 1 Budgeted Cost $ 20,000 Required: 1. Classify each of the three overhead activities as unit level, batch level, product level, or facility level. 2. Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product cost of Job 615. Department 3. Assume Business Solutions uses activity-based costing. (a) Compute overhead activity rates. (b) Allocate overhead cost to Job 615. (c) Compute total product cost of Job 615. Job 615 7,500 10,000 $ 37,500 F2 Required 2 Job 615 Total product cost of Job 615 W Assume Business Solutions allocates overhead cost using a plantwide rate based on 5,000 machine hours. Compute total product cost of Job 615. (Round "Overhead rate" to 2 decimal places.) Allocate overhead to Job 615 using plantwide rate Machine Hours Used $ # 3 $ 2,500 $ 3,500 Plantwide Overhead Rate Direct Materials 20 F3 E 2 setups 400 parts inspected 600 machine hours Required 3 S D Budgeted Activity Usage 25 setups 5,000 parts inspected 5,000 machine hours (MH) Direct Labor 4 F4 R F Overhead Allocated Overhead % 5 Product Cost $ Ų F5 T G 0 Prev <6 1 of 4 MacBook Air F6 Y & 7 H Next > F7 U * 00 8 J DII F8 - ( 9 F9 K -O O 0
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education