The Chiemsee Knee Replacement Clinic (CKRC) is a sports clinic located at the northern edge of the German Alps. It specializes in knee replacements for skiers who come to CKRC from Germany, Austria, Switzerland, and Italy. The clinic currently has one operating room (OR). However, since the clinic has dramatically more demand than capacity, the management team contemplates investing in a second OR. A lean consulting firm, however, suggests that before going ahead with installing new capacity, the clinic should first look at how it uses its existing capacity. The data collected by the consulting firm reveal that: The OR is available for 12 hours a day; the hospital has decided to not perform any procedures between 7pm and 7am. This time is equally divided across three surgeons. The standard procedure time for the knee surgery done at the clinic is 1h. The cleaning and housekeeping that needs to happen after each procedure takes 20 minutes. Almost all of this time could be saved if the cleaning crew were notified earlier on. 10 minutes are spent on patient preparation / anesthesia work before each procedure. (Note: this is not part of the 60-minute procedure time). Proposals have been evaluated to move these 10 minutes to outside the OR, and there exists no medical reason that would prohibit doing this.) A surgeon only starts a case if all of the work associated with the case (preparation, procedure, and cleaning) can be completed in the 4h allotted to each surgeon. Surgeons never start BEFORE their allotted time. Though the clinic aims to operate 7 days a week, holidays, vacation, and construction time lead to an average of one day a week that the OR cannot be used at all. What is the OEE of the operating room? Assume a 12h window in which the OR could be used.
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
The Chiemsee Knee Replacement Clinic (CKRC) is a sports clinic located at the northern edge of the German Alps. It specializes in knee replacements for skiers who come to CKRC from Germany, Austria, Switzerland, and Italy. The clinic currently has one operating room (OR). However, since the clinic has dramatically more demand than capacity, the management team contemplates investing in a second OR. A lean consulting firm, however, suggests that before going ahead with installing new capacity, the clinic should first look at how it uses its existing capacity. The data collected by the consulting firm reveal that:
- The OR is available for 12 hours a day; the hospital has decided to not perform any procedures between 7pm and 7am. This time is equally divided across three surgeons.
- The standard procedure time for the knee surgery done at the clinic is 1h.
- The cleaning and housekeeping that needs to happen after each procedure takes 20 minutes. Almost all of this time could be saved if the cleaning crew were notified earlier on.
- 10 minutes are spent on patient preparation / anesthesia work before each procedure. (Note: this is not part of the 60-minute procedure time). Proposals have been evaluated to move these 10 minutes to outside the OR, and there exists no medical reason that would prohibit doing this.)
- A surgeon only starts a case if all of the work associated with the case (preparation, procedure, and cleaning) can be completed in the 4h allotted to each surgeon. Surgeons never start BEFORE their allotted time.
- Though the clinic aims to operate 7 days a week, holidays, vacation, and construction time lead to an average of one day a week that the OR cannot be used at all.
What is the OEE of the operating room? Assume a 12h window in which the OR could be used.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images