The activities, duration, and cost under normal and accelerated crashed conditions for a network diagram are shown in the accompanying tabl Duration, days Cost, pesos Activity Node Accelerated Normal Accelerated A 1 to 2 2 6800 7200 8 2 to 3 24200 26800 C 2 to 4 4 8000 8000 4 to 3 3 6000 6900 3 to 5 2 5800 5800 5 to 6 4 7200 7550 3 to 7 3 8400 9000 7 10 6 1 4500 5200 6 to 8 5 9300 9700 3 to 9 5 5300 5900 9 to 10 7 29100 32100 8 to 10 1 1200 1200 10 to 11 2 8700 9000 D E F H I J K L M Normal 3 8 6 2 5 2 7 10 1 3

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

The activities, duration, and cost under normal and accelerated (crashed) conditions for a network diagram are shown in the accompanying table.

 

 

 

1. Determine the critical path of the project under normal conditions 

2. Determine the duration of the project under normal conditions 

3. Determine the cost of the project under normal conditions 

4. Determine the minimum duration of the project 

5. Determine the cost of the project when the duration is minimum? 

 

Notes on answering:

For answering critical path, answer in capital letters only without hyphens,dashes,commas, or any symbols (i.e., ABJKM, AFLKO)

For answering durations and costs, answer in numerical value only without units. (i.e., for durations: 16, 12, 15. for costs: 12000,1500,17500)

Not following instructions in answering will not be considered

The activities, duration, and cost under normal and accelerated crashed conditions for a
network diagram are shown in the accompanying table
Duration, days
Cost, pesos
Activity
Node
Accelerated Normal
A
1 to 2
2
6800
B
2 to 3
6
24200
C
2 to 4
8000
4 to 3
6000
3 to 5
5800
5 to 6
7200
3 to 7
8400
7 to 6
4500
6 to 8
9300
3 to 9
5300
9 to 10
29100
8 to 10
1200
10 to 11
8700
D
t
F
G
H
I
J
K
L
M
Normal
3
2
5
4
2
7
10
1
3
4
3
2
4
3
1
S
5
7
1
2
Accelerated
7200
26800
8000
6900
5800
7550
9000
5200
9700
5900
32100
1200
9000
Transcribed Image Text:The activities, duration, and cost under normal and accelerated crashed conditions for a network diagram are shown in the accompanying table Duration, days Cost, pesos Activity Node Accelerated Normal A 1 to 2 2 6800 B 2 to 3 6 24200 C 2 to 4 8000 4 to 3 6000 3 to 5 5800 5 to 6 7200 3 to 7 8400 7 to 6 4500 6 to 8 9300 3 to 9 5300 9 to 10 29100 8 to 10 1200 10 to 11 8700 D t F G H I J K L M Normal 3 2 5 4 2 7 10 1 3 4 3 2 4 3 1 S 5 7 1 2 Accelerated 7200 26800 8000 6900 5800 7550 9000 5200 9700 5900 32100 1200 9000
1. Determine the critical path of the project under normal conditions
2. Determine the duration of the project under normal conditions
3. Determine the cost of the project under normal conditions
4. Determine the minimum duration of the project
5. Determine the cost of the project when the duration is minimum?
Notes on answering
For answering critical path answer in capital letters only without hyphens.dashes.commasor
any symbols, ABKM, AFLKD)
For answering durations and costs, answer in numerical value only without units. Gie, for
duration: 16, 12, 15, for costs: 12000.1500175001
Not following instructions in answering will not be considered
Transcribed Image Text:1. Determine the critical path of the project under normal conditions 2. Determine the duration of the project under normal conditions 3. Determine the cost of the project under normal conditions 4. Determine the minimum duration of the project 5. Determine the cost of the project when the duration is minimum? Notes on answering For answering critical path answer in capital letters only without hyphens.dashes.commasor any symbols, ABKM, AFLKD) For answering durations and costs, answer in numerical value only without units. Gie, for duration: 16, 12, 15, for costs: 12000.1500175001 Not following instructions in answering will not be considered
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Cost control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning