Concept explainers
Stelle Technology has a contract to build a network for a customer for a total sales price of €10 million. Th e network will take an estimated three years to build, and total building costs are estimated to be €6 million. Stelle recognizes long-term contract revenue using the percentage-of-completion method and estimates percentage complete based on expenditure incurred as a percentage of total estimated expenditures. 1 . At the end of Year 1, the company had spent €3 million. Total costs to complete are estimated to be another €3 million. How much revenue will Stelle recognize in Year 1? 2 . At the end of Year 2, the company had spent an additional €2.4 million for an accumulated total of €5.4 million. Total costs to complete are estimated to be another €0.6 million. How much revenue will Stelle recognize in Year 2? 3 . At the end of Year 3, the contract is complete. Th e company spent an accumulated total of €6 million. How much revenue will Stelle recognize in Year 3?
Step by stepSolved in 2 steps
- Cerise Ltd (Cerise) has a year end of 30 April 2021. The company begandeveloping a project on 1 May 2020, incurring total development costs up to the year end of £270,000 which were incurred evenly throughout the year. Cerise also incurred a one-off training expense for its employees to learn how to use the new product, costing £12,000 on 13 March 2021. This was incurred in addition to the £270,000 development costs.The relevant criteria for capitalisation according to IAS 38 Intangible Assetshave been met by project Magenta from 1 January 2021. How much would be eligible for capitalisation for this project for the year ended 30 April 2021?a) £270,000b) £78,000c) £90,000d) £102,000 Which option is correct and whyarrow_forwardThe Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involves a cash outlay of $270,000 at the end of each of the next two years. At the end of the third year, the company will receive payment of $620,000. The company can speed up construction by working an extra shift. In this case, there will be a cash outlay of $584,000 at the end of the first year followed by a cash payment of $620,000 at the end of the second year. Use the IRR rule to show the (approximate) range of opportunity costs of capital at which the company should work the extra shift. Note: Enter your answers as a percent rounded to 2 decimal places. Enter the smallest percent first. The company should work the extra shift if the cost of capital is between % and %.arrow_forwardSheridan Construction Company has entered into a contract beginning January 1, 2025, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date (a) $256,280 339,720 270,000 Gross profit recognized in 2025 Gross profit recognized in 2026 2025 Sok and Media 240,000 Gross profit recognized in 2027 $ GA $ LA 2026 Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter O. Do not leave any fields blank.) 5 $429,120 166,880 555,000 505,000 2027 $606,000 902,000 902.000arrow_forward
- Lockheed Martin has secured a satellite launch contract from a European communications company that will pay them € 3.9M per year for the next 8 years . To land that contract , they invested € 13M in a satellite tracking system . Of that amount , €8M was paid up front and the remaining €5M was spent during the first year of operation . The annual operating costs for the satellite tracking system are estimated at € 0.9M per year ( which includes the cost of personnel , electricity , maintenance , etc. ) . At the end of the contract , it is estimated that the equipment will have a salvage value of € 0.5M . What is Lockheed Martin's internal rate of return ( IRR ) on this project ?arrow_forwardA construction company entered into a fixed-price contract to build an office building for $42 million. Construction costs incurred during the first year were $12 million, and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? Note: Enter your answers in whole dollars and not in millions (i.e., $4 million should be entered as $4,000,000). Revenuearrow_forwardXtra Mechanical, Inc. is a manufacturer of machine parts with locations in the United States. It is considering entering into an eight year supply agreement with a customer where it will supply certain parts to the customer for their products. The project will require Xtra to purchase a new machine at the begining of the project and the cost of the machine is $8,500,000. At the end of the project, the machine is expected to be sold in the used market for 20% of the original cost before paying taver. The five year MACRS depreciation will be used for tax purposes. The depreciate rates are shown below. There is an initial networking capital investment of $15,000 and no further investment in not working capital is required. We assume that all the money tied up in the networking capital account will be recovered by the end of the project Revenues from the contract per year are shown below. Cost of goods sold is expected to be 50% of revenues. In addition to cost of goods seld, the project…arrow_forward
- Caramel Spa Company sells prefabricated pools that cost $80,000 to customers for $144,000. The sales price includes an installation fee, which is valued at $20,000. The fair value of the pool is $128,000. The installation is considered a seperate performance obligation and is expected to take 3 months to complete. The transaction price allocated to the pool and the installation isarrow_forwardShumpert, Inc. entered into a contract that was to take two years to complete, with an estimated cost of $2,257,600. The contract price was $3,160,640. Costs of the contract for 2014, the first year, totaled $1,693,200. a. What was the gross profit reported by the percentage of completion method for 2014?arrow_forward
- Essentials Of InvestmentsFinanceISBN:9781260013924Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.Publisher:Mcgraw-hill Education,
- Foundations Of FinanceFinanceISBN:9780134897264Author:KEOWN, Arthur J., Martin, John D., PETTY, J. WilliamPublisher:Pearson,Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage LearningCorporate Finance (The Mcgraw-hill/Irwin Series i...FinanceISBN:9780077861759Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan ProfessorPublisher:McGraw-Hill Education