Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Actual costs 1,550 lbs. at $9.10 Standard costs 1,600 lbs. at $9.00 Determine the direct materials (a) quantity variance, (b) price variance, and (c) total cost variance.
Q: Standard and actual costs for direct labor for the manufacture of 1,500 units of product were as…
A: Direct labor time variance: The difference between the actual time spent manufacturing a specific…
Q: The standard cost of Product B manufactured by Bramble Company includes 2.30 units of direct…
A: Total material variance = Standard material cost - Actual material cost Material price variance =…
Q: Hardin Company has the following information available for the current year: Standard:…
A: Material Price Variance (MPV) = (Standard Price – Actual Price) x Actual Quantity…
Q: In a period, 11,280 kg of material were used and should have cost (according to the standard cost…
A: Material usage variance is the difference between standard quantity of material for actual output…
Q: The standard cost of product 777 includes 2.1 units of direct materials at $6.00 per unit. During…
A: Materials price variance = (Standard price - Actual price) x Actual quantity Materials quantity…
Q: Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as…
A: Quantity variance=Standard quantity-Actual quantity×Standard Price Price variance=Standard…
Q: The standard costs and actual costs for direct materials for the manufacture of 1,870 actual units…
A: The direct material quantity variance is calculated as difference of standard cost at standard…
Q: The standard composition of material that is used in the production of product ‘Flurry’ is as…
A: Standard costing means where standard is set for various cost element and actual cost is then…
Q: The data below relate to the standards for the sole product of Marshal Corporati August: Standard…
A: The difference between a standard and an actual value is called variance and can be favorable or…
Q: The data below relate to the standards for the sole product of Marshal Corporation in August:…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: The standard quantity allowed for the units produced was 4,500 pounds, the standard price was P2.50…
A: Standard quantity allowed for actual production =4500 pounds Standard quantity per unit = 1 pound
Q: Reed Corp. has set the following standard direct materials and direct labor costs per unit for the…
A: Definition: Direct material variances: The difference between the actual material cost per unit and…
Q: The standard costs and actual costs for direct materials for the manufacture of 2,000 actual units…
A: Formula to calculate direct material quantity variance:Direct material quantity variance = (Standard…
Q: The standard cost of Product B manufactured by Pharrell Company includes 2.4 units of direct…
A: Answer a) Total material variance =Standard Cost - Actual Cost=(11100 x 2.4 x 5.1) -(27000 x…
Q: Standard and actual costs for direct materials for the manufacture of 2,000 units of product were as…
A: Quantity variance=Standard quantity-Actual quantity×Standard Price Price variance=Standard…
Q: Myers Corporation has the following data related to direct materials costs for November: actual cost…
A: Formula: Direct Material price variance = (Actual price per pound - Standard price per pound)*Actual…
Q: he standard costs and actual costs for direct materials for the manufacture of 2,800 actual units of…
A: Variance analysis is a type of analysis that is used to distinguish between actual and planned…
Q: The Company has collected the following data for one its line of products: Direct materials…
A: Variance refers to a change between the expected value and the actual result. This term is usually…
Q: Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as…
A: Calculate the quantity variance as follows : Quantity variance is calculated as a product of the…
Q: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units…
A: Direct materials price variance = ( Standard rate of material - Actual rate of material ) x Actual…
Q: A manufacturing company reports the following for one of its products. Compute the direct materials…
A:
Q: NUBD Corporation’s variance report for the purchasing department reports 500 units of material A…
A: Formula: Material Price variance = ( Actual Quantity x Actual price ) - ( Actual quantity x standard…
Q: The following data relate to direct materials costs for February: Materials cost per yard:…
A: Material Price Variance measures variance arises in the material cost due to difference in actual…
Q: Myers Corporation has the following data related to direct materials costs for November: actual cost…
A: Direct material price variance = (Standard Price - Actual Price) x Actual Quantity Variance is…
Q: Tercer reports the following for one of its products. Compute the direct materials price and…
A: Compute the direct materials price and quantity variances and classify each as favorable or…
Q: A company provided the following direct materlals cost Information. Compute the total direct…
A: Solution: Total direct material variance is the difference between standard cost of material and…
Q: The standard price per kilogram for the raw material must be
A: Computation of standard price per kilogram (SP) is shown below :
Q: direct materials quantity variance
A: Direct materials quantity variance = (Standard Quantity - Actual Quantity) * Standard Price where,…
Q: The standard costs and actual costs for direct materials for the manufacture of 1,870 actual units…
A: Direct Material quantity variance = (Actual quantity used - Standard quantity allowed)*Standard…
Q: The standard quantity allowed for the units produced was 4,500 pounds, the standard price was P2.50…
A: Solution: Standard quantity for actual production = 4500 pound Standard quantity per units produced…
Q: The standard and actual prices per pound of raw material are $4.00 and $4.50,respectively. A total…
A:
Q: Eric Limited provides the following data for the month of March: Particulars Standard Actual…
A: The raw material cost variance refers to the difference between the actual cost and standard cost of…
Q: Elder furnishes the following information for the year. Standard: Material for 70 kgs finished…
A: Formulas: Material usage variance =(Standard quantity - Actual quantity)* standard price Material…
Q: Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as…
A: Quantity variance is the difference between the actual usage and the expected usage. Price…
Q: The standard costs and actual costs for direct materials for the manufacture of 2,430 actual units…
A: The variance is the difference between standard and the actual output of the production.
Q: The Russell Company provides the following standard cost data per unit of product: Direct…
A: Direct material usage variance helps to determine the difference between the standard quantity of…
Q: Standard and actual costs for direct labor for the manufacture of 1,500 units of product were as…
A: Variance: Variance refers to the difference level in the actual cost incurred and standard cost. The…
Q: The standard cost card for product Alpha is as follows: £ Direct material 5kg@ £11.50…
A: Lets understand the basics. Direct material price variance is variance between the rate at which…
Q: Myers Corporation has the following data related to direct materials costs for November: actual…
A: Direct materials quantity variance = (Actual quantity - Standard quantity)*Standard price
Q: Starts Inc. produces a product for which the standard specifies 8 yards of material per unit. The…
A: Standard costing: Under this costing method, the expected costs are used in the accounting records…
Q: The standard costs and actual costs for direct materials for the manufacture of 2,000 actual units…
A: Formula to calcualte Direct material price variance:Direct material price variance = (Standard price…
Q: Given the following information, calculate the materials price variance: Direct material…
A: Material price variance is that part of material cost variance which is due to the difference…
Q: A company provided the following direct materials cost information. Compute the direct materials…
A: DIRECT MATERIAL QUANTITY VARIANCE : = ( ACTUAL QUANTITY OF MATERIAL USED FOR UNITS PRODUCED -…
Q: Standard and actual costs for direct labor for the manufacture of 300 units of product were as…
A:
Q: Use the information that is given below and calculate the Period Cost.…
A: Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Starts Inc. produces a product for which the standard specifies 4 yards of material per unit. The…
A: As posted multiple sub parts we are answering only first three sub parts kindly repost the…
Q: A company provided the following direct materials cost information. Compute the direct materials…
A: Direct material quantity variance = Standard price ×[Actual quantity - Standard quantity]
Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows:
Actual costs | 1,550 lbs. at $9.10 |
1,600 lbs. at $9.00 |
Determine the direct materials (a) quantity variance, (b) price variance, and (c) total cost variance.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Actual costs 1,540 lbs. @ $9.15 Standard costs 1,600 lbs. @ $9.00 Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance. For each variance, indicate if the variance is favorable or unfavorable. (a) (b) (c)Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Actual costs 1,450 lbs. @ $8.10 Standard costs 1,500 lbs. @ $8.00 Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance. a. Quantity variance $ b. Price variance $ c. Total direct materials cost variance $Given the following information: 2a) the standard material costs of finished product X are as follows 2kg raw material Y @R10 per kg Actual information Purchases of raw material Y 1000kg @R9, 50 per kg Issues of raw material Y 600 kg Units of product X manufactured 290 units Calculate the following variances in respect of material i) Purchase price variance ( 5) ii) Issue price variance (5) iii) Quantity variance (5) iv) Total material variance if an issue price variance is used (5)
- Based on the following information, calculate the direct materials price variance. Actual costs 3,590 pounds at $8.00 Standard costs 4,100 pounds at $6.00Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Actual costs 1,450 lbs. @ $8.10 Standard costs 1,500 lbs. @ $8.00 Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance. a. Quantity variance $fill in the blank 1 b. Price variance $fill in the blank 2 c. Total direct materials cost variance $fill in the blank 3The standard costs and actual costs for direct materials for the manufacture of 1,870 actual units of product are as follows: Standard Costs Direct materials 1,870 kilograms at $8.60 Actual Costs Direct materials 2,000 kilograms at $8.05 The direct materials quantity variance is
- Standard and the actual costs for direct materials and direct labor are given as under:Standard costsDirect materials 8,000 units at total direct material costs Rs. 40,000Direct labor: 7,000 hours at Rs. 6 per hour Actual costsDirect materials 8,500 units at Rs. 4.5 per unitDirect labor: 6,500 hours at Rs. 6.25 per hour Requireda. Material Price Variance and Material Quantity Varianceb. Labor Rate Variance and Labor Efficiency Variance c. Entries in general journal to record the above informationd. What do you realize whether the overall variation is in favorable or unfavorable?Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Actual costs 1,450 lbs. @ $8.10 Standard costs 1,500 lbs. @ $8.00 Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance. a. Quantity variance $400 b. Price variance $fill in the blank 2 c. Total direct materials cost variance $fill in the blank 3Assume the following information (the quantity of materials purchased the quantity used): Actual total cost of direct materials Direct materials price variance Standard quantity of materials allowed per unit Standard price per pound of material Standard rate per direct labor hour Actual total direct labor hours Direct labor efficiency variance Standard number of direct labor hours allowed per unit. Direct labor spending variance What is the standard price (SP) per pound of materials? $ 65,560 $ 5,960 U 3 pounds $ 4.00 $ 5.00 6,500 $ 3,500 F 2 hours $ 400 U
- The standard costs and actual costs for direct materials for the manufacture of 2,780 actual units of product are as follows: Standard Costs Direct materials Direct materials 2,780 kilograms at $8.70 Actual Costs 2,900 kilograms at $8.05 The direct materials quantity variance is Oa. $835 unfavorable Ob. $1,044 unfavorable Oc. $1,044 favorable Od. $835 favorableThe standard costs and actual costs for direct materials for the manufacture of 1,870 actual units of product are Standard Costs Direct materials 1,870 kilograms @$8.90 Actual Costs Direct materials 2,000 kilograms @ $8.25 The amount of the direct materials quantity variance isAcme Inc. has the following information available: Actual price paid for material Standard price for material Actual quantity purchased and used in production Standard quantity for units produced Actual labor rate per hour Standard labor rate per hour Actual hours Standard hours for units produced Variance Material Price NOTE: All dollar amounts are rounded to whole dollars and shown with "$" and commas as needed (i.e. $12,345). For the variance conditions, your answer is either "F" (for Favorable) or "U" (for Unfavorable) - capital letter and no quotes. Complete the following table of variances and their conditions: Material Quantity Total DM Cost Variance Labor Rate Labor Efficiency Total DL Cost Variance $1.00 $0.90 100 90 15 14 Variance Amount $ $ 200 190 Favorable (F) or Unfavorable (U)