Question 2 When providing controls for a construction project, a link traverse that consists of points 1, 2, 3, 4, 5 6, 7 and 8 was established. The data is as shown in Table Q2. Calculate the linear misclosre of the traverse and the final coordinates of the unknown stations. Table Q2 Known Back Bearing at Stn. 1 Known Fwd Bearing at Stn. 8 Station Left hand angle 35° 10' 22" 288° 13' 09" Traverse Leg Distance 1 89 01 14 1-2 461.351 2 111 32 46 2-3 95.450 3 146 44 36 3-4 90.689 4 151 54 29 4-5 116.119 5 166 38 22 5-6 146.119 6 156 20 05 6-7 100.156 7 173 11 31 7-8 103.432 8 157 39 44 Coordinates of Stn. 1 (N,E) 5000.000 5000.000 Coordinates of Stn. 8 (N,E) 5272.899 5289.896

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Question 2
When providing controls for a construction project, a link traverse that consists of points 1, 2, 3, 4, 5
6, 7 and 8 was established. The data is as shown in Table Q2.
Calculate the linear misclosre of the traverse and the final coordinates of the unknown stations.
Table Q2
10' 22"
Known Back Bearing at Stn. 1
Known Fwd Bearing at Stn. 8
Station
Left hand angle
35°
288°
Traverse Leg
13' 09"
Distance
1
89
01
14
1-2
461.351
2
111
32
46
2-3
95.450
3
146
44 36
3-4
90.689
4
151
54 29
4-5
116.119
5
166
38 22
5-6
146.119
6
156
20
05
6-7
100.156
7
173
11 31
7-8
103.432
8
39 44
157
Coordinates of Stn. 1 (N,E)
Coordinates of Stn. 8 (N,E)
5000.000
5000.000
5272.899
5289.896
Transcribed Image Text:Question 2 When providing controls for a construction project, a link traverse that consists of points 1, 2, 3, 4, 5 6, 7 and 8 was established. The data is as shown in Table Q2. Calculate the linear misclosre of the traverse and the final coordinates of the unknown stations. Table Q2 10' 22" Known Back Bearing at Stn. 1 Known Fwd Bearing at Stn. 8 Station Left hand angle 35° 288° Traverse Leg 13' 09" Distance 1 89 01 14 1-2 461.351 2 111 32 46 2-3 95.450 3 146 44 36 3-4 90.689 4 151 54 29 4-5 116.119 5 166 38 22 5-6 146.119 6 156 20 05 6-7 100.156 7 173 11 31 7-8 103.432 8 39 44 157 Coordinates of Stn. 1 (N,E) Coordinates of Stn. 8 (N,E) 5000.000 5000.000 5272.899 5289.896
Expert Solution
steps

Step by step

Solved in 5 steps with 1 images

Blurred answer
Knowledge Booster
Adjusting observations
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning