Q1 Quick Konstruct builds custom, high-end homes. Each home requires a bid, and Quick's bidding practise is to estimate the costs of materials, direct labour and subcontracting fees. These are totalled and markup is applied to cover overhead and profit. In the next year, Quick belleves it will be the successful bidder on 10 jobs with the following total revenues and costs: $648,000 tructions a) b) The excess is created to cover overhead and profits. a) Revenues Materials Direct labour Subcontractors Excess b) $200,000 $250,000 $150,000 Answer below: What is the markup percentage on total direct costs? If Quick is asked to bid on a job with estimated direct costs of $55,000, what is the amount of the total bid? If the customer complains that the profit is too high, how might Quick counter that comment? Show Calculations. Answer below: $600,000 $48,000 Show Calculations 4

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter18: Pricing And Profitability Analysis
Section: Chapter Questions
Problem 13E
icon
Related questions
Question

help

 

Q1 Quick Konstruct builds custom, high-end homes. Each home requires a bid, and Quick's bidding
practise is to estimate the costs of materials, direct labour and subcontracting fees. These are
totalled and markup is applied to cover overhead and profit. In the next year, Quick believes it
will be the successful bidder on 10 jobs with the following total revenues and costs:
structions
a)
b)
Revenues
Materials
Direct labour
Subcontractors
Excess
The excess is created to cover overhead and profits.
b)
$200,000
$250,000
$150,000
Answer below:
Answer below:
What is the markup percentage on total direct costs?
If Quick is asked to bid on a job with estimated direct costs of $55,000,
what is the amount of the total bid? If the customer complains that the profit is too high,
how might Quick counter that comment?
+
Show Calculations
$648,000
Show Calculations
$600,000
$48,000
Transcribed Image Text:Q1 Quick Konstruct builds custom, high-end homes. Each home requires a bid, and Quick's bidding practise is to estimate the costs of materials, direct labour and subcontracting fees. These are totalled and markup is applied to cover overhead and profit. In the next year, Quick believes it will be the successful bidder on 10 jobs with the following total revenues and costs: structions a) b) Revenues Materials Direct labour Subcontractors Excess The excess is created to cover overhead and profits. b) $200,000 $250,000 $150,000 Answer below: Answer below: What is the markup percentage on total direct costs? If Quick is asked to bid on a job with estimated direct costs of $55,000, what is the amount of the total bid? If the customer complains that the profit is too high, how might Quick counter that comment? + Show Calculations $648,000 Show Calculations $600,000 $48,000
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Business analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning