Q 2. Schedule the precedence diagram for the following project. This problem is to be solved using MS Project program. Activity List for a Reroofing Project Activity Description 1 Mobilize Duration Days Predecessors 1 2 Set up scaffolding 2 3 Construct security barricades 1 4 Strip off old roofing 3 1 2 SS/1 2,3 5 Repair damaged decking 2 4 SS/1 6 Repair damaged cant strip 1 4,5 7 Replace sheet metal 1 5 SS/1 8 Install felt roofing 1 6,7 9 Hot mop roof 10 Inspect roofing 11 Call for inspection 2 1 1 8 9 10 SF/3 12 Remove scaffolding 13 Haul off roofing materials 2 10 2 6,7 1 12 FF/1, 13 FF/1 14 Demobilize "Under Predecessors, the following notation is used: x/#: Activity x must finish # days before this activity can begin. xSS/#: The # of days after activity x starts that this activity can begin. xFF/#: This activity cannot finish until # days after x is completed. XSF/#: This activity must finish # days before x can start.

Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter7: Introduction To Residential Service Entrances
Section: Chapter Questions
Problem 26RQ
icon
Related questions
Question

Using MS Project schedule the precedence diagram for the project 

 

Q 2. Schedule the precedence diagram for the following project. This problem is to be
solved using MS Project program.
Activity List for a Reroofing Project
Activity Description
1 Mobilize
Duration Days
Predecessors
1
2 Set up scaffolding
2
3 Construct security barricades
1
4 Strip off old roofing
3
1
2 SS/1
2,3
5 Repair damaged decking
2
4 SS/1
6 Repair damaged cant strip
1
4,5
7 Replace sheet metal
1
5 SS/1
8 Install felt roofing
1
6,7
9 Hot mop roof
10 Inspect roofing
11 Call for inspection
2
1
1
8
9
10 SF/3
12 Remove scaffolding
13 Haul off roofing materials
2
10
2
6,7
1
12 FF/1, 13 FF/1
14 Demobilize
"Under Predecessors, the following notation is used:
x/#: Activity x must finish # days before this activity can begin.
xSS/#: The # of days after activity x starts that this activity can begin.
xFF/#: This activity cannot finish until # days after x is completed.
XSF/#: This activity must finish # days before x can start.
Transcribed Image Text:Q 2. Schedule the precedence diagram for the following project. This problem is to be solved using MS Project program. Activity List for a Reroofing Project Activity Description 1 Mobilize Duration Days Predecessors 1 2 Set up scaffolding 2 3 Construct security barricades 1 4 Strip off old roofing 3 1 2 SS/1 2,3 5 Repair damaged decking 2 4 SS/1 6 Repair damaged cant strip 1 4,5 7 Replace sheet metal 1 5 SS/1 8 Install felt roofing 1 6,7 9 Hot mop roof 10 Inspect roofing 11 Call for inspection 2 1 1 8 9 10 SF/3 12 Remove scaffolding 13 Haul off roofing materials 2 10 2 6,7 1 12 FF/1, 13 FF/1 14 Demobilize "Under Predecessors, the following notation is used: x/#: Activity x must finish # days before this activity can begin. xSS/#: The # of days after activity x starts that this activity can begin. xFF/#: This activity cannot finish until # days after x is completed. XSF/#: This activity must finish # days before x can start.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning