pofing 1. Formwork of footing FOOTING Vc=60 cu.m. Steel reinforcement= 3800 kg Formwork area= 10 sq.m. 2. Steelworks steel reinforcement Number of gang(output of tHe gang) duration of steelworks : 3. Pouring of concrete vol of concrete duration of pouring of concrete = - Number of gang(output of tHe gang) 4. Stripping of formworks area to be stripped duration of stripping = Number of gang(output of tHe gang)

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter4: Mechanical Processes
Section: Chapter Questions
Problem 4.13P
icon
Related questions
Question
100%

Compute for the duration with the given

Footing
1. Formwork of footing
FOOTING
Vc=60 cu.m.
Steel reinforcement= 3800 kg
Formwork area= 10 sq.m.
2. Steelworks
steel reinforcement
duration of steelworks
Number of gang(output of tHe gang)
3. Pouring of concrete
vol of concrete
duration of pouring of concrete
Number of gang(output of tHe gang)
4. Stripping of formworks
area to be stripped
duration of stripping = Number of gang(output of tHe gang)
Transcribed Image Text:Footing 1. Formwork of footing FOOTING Vc=60 cu.m. Steel reinforcement= 3800 kg Formwork area= 10 sq.m. 2. Steelworks steel reinforcement duration of steelworks Number of gang(output of tHe gang) 3. Pouring of concrete vol of concrete duration of pouring of concrete Number of gang(output of tHe gang) 4. Stripping of formworks area to be stripped duration of stripping = Number of gang(output of tHe gang)
ITEM 404 : REINFORCING STEEL BAR
A. Materials:
A.1. Tie Wires: 15 kgs. Per ton of steel bar
B. Labor: (Cutting, bending, fabrication, installation & other miscellaneous works)
B.1. Crew Composition; (Minimum composition)
1- Civil Engineer
1- Construction Foreman
2- Steelman
2- Skilled Laborers
6- Laborers
B.2. Capacity of gang = 750 kg,/day
C. Equipment required per gang
1- unit Bar Cutter,
STRIPPING OF FORMWORK FACTOR FOR THE GANG
D. Formworks:
D.1. Formworks:
Minimum Crew Composition:
1- Civil Engineer
1- Construction Foreman
2- Carpenters
4- Laborers
Сараcity.
1. Fabrication and Installation = 35 sq. m./day
2. Stripping
= 60 sq. m/day
Transcribed Image Text:ITEM 404 : REINFORCING STEEL BAR A. Materials: A.1. Tie Wires: 15 kgs. Per ton of steel bar B. Labor: (Cutting, bending, fabrication, installation & other miscellaneous works) B.1. Crew Composition; (Minimum composition) 1- Civil Engineer 1- Construction Foreman 2- Steelman 2- Skilled Laborers 6- Laborers B.2. Capacity of gang = 750 kg,/day C. Equipment required per gang 1- unit Bar Cutter, STRIPPING OF FORMWORK FACTOR FOR THE GANG D. Formworks: D.1. Formworks: Minimum Crew Composition: 1- Civil Engineer 1- Construction Foreman 2- Carpenters 4- Laborers Сараcity. 1. Fabrication and Installation = 35 sq. m./day 2. Stripping = 60 sq. m/day
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Estimating construction costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,