|At a particular time during the construction, the site manager realizes that the actual excavation will be in the range of 110,000 cubic yards. Based on the new quantity, he figures that he will have 30,000 cubic yards left. From the main office, the following job information is available:

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 4RQ
icon
Related questions
Question

17.6 The following planned figures for a trenching job are available:

Quantity                                            Resources(hours)                          Cost

Excavation—second                       Machines1000                                  $100,000

Hauling                                             

Labor 5000                                        $100,000

100,000 cubic yard                          Trucks 2000                                      $ 62,500

At a particular time during the construction, the site manager realizes that the actual excavation will be in the range of 110,000 cubic yards. Based on the new quantity, he figures that he will have 30,000 cubic yards left.

From the main office, the following job information is available:

Resources                                                    Cost

Machines                   895 hours                  85000

Labor                          6011 work hours       79000

Trucks                        1684 hours                50140

What would concern you as manager of this job?

17.6 The following planned figures for a trenching job are
available:
Quantity
Resources (hours)
Cost
Excavation-second
Machines 1000
$100,000
hauling
Labor 5000
$100,000
100,000 cubic yard
Trucks 2000
$ 62,500
JAt a particular time during the construction, the site
manager realizes that the actual excavation will be in the range
of 110,000 cubic yards. Based on the new quantity, he figures
that he will have 30,000 cubic yards left.
From the main office, the following job information is
available:
Resources
Cost
Machines
895 hours
85000
Labor
6011 work hours
79000
Trucks
1684 hours
50140
What would concern you as manager of this job?
Transcribed Image Text:17.6 The following planned figures for a trenching job are available: Quantity Resources (hours) Cost Excavation-second Machines 1000 $100,000 hauling Labor 5000 $100,000 100,000 cubic yard Trucks 2000 $ 62,500 JAt a particular time during the construction, the site manager realizes that the actual excavation will be in the range of 110,000 cubic yards. Based on the new quantity, he figures that he will have 30,000 cubic yards left. From the main office, the following job information is available: Resources Cost Machines 895 hours 85000 Labor 6011 work hours 79000 Trucks 1684 hours 50140 What would concern you as manager of this job?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,