On a unit-price contract, if a contractor includes a unitprice of $145.00 per meter for 765 meters of pipe to be constructed in place, but incorrectly shows the extended amount as $110,952.00, exactly how much money should be included in the total bid price?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question

On a unit-price contract, if a contractor includes a unitprice of $145.00 per meter for 765 meters of pipe to be constructed in place, but incorrectly shows the extended amount as $110,952.00, exactly how much money should be included in the total bid price?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Bid package
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,