manufacturer is designing a product layout for a new product production. It plans to use a production line r 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in tal. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to art. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. so, starting task D needed task B to be completed. Task E can only start upon completion of Task C. "hereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 inutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken Ccording to longest task time first, the tasks that will be assigned to the FIRST workstation are elect one: O a. None is the correct answer

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Topic Video
Question
A manufacturer is designing a product layout for a new product production. It plans to use a production line
for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in
total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to
start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed.
Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C.
Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task
F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7
minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken
according to longest task time first, the tasks that will be assigned to the FIRST workstation are
Select one:
Oa. None is the correct answer
O b. A only
C. A, B, and C
O d. A, B
Transcribed Image Text:A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one: Oa. None is the correct answer O b. A only C. A, B, and C O d. A, B
FACTORS FOR R CHARTS
Number of
Factor for
Observations
in Subgroup,
x Chart,
A2
Lower
Control Limit,
Upper
Control Limit,
D3
Da
1.88
3.27
1.02
2.57
0.73
0.58
2.28
4
2.11
5
0.48
2.00
0.42
0.08
1.92
0.37
0.14
1.86
8
0.34
0.18
1.82
0.31
0.22
1.78
10
0.29
0.26
1.74
11
0.27
0.28
1.72
12
0.31
1.69
0.25
13
0.24
0.33
1.67
14
0.22
0.35
1.65
15
0.36
1.64
0.21
16
0.38
1.62
17
0.20
0.39
1.61
18
0.19
0.40
1.60
19
0.19
0.41
1.59
20
0.18
23
67
Transcribed Image Text:FACTORS FOR R CHARTS Number of Factor for Observations in Subgroup, x Chart, A2 Lower Control Limit, Upper Control Limit, D3 Da 1.88 3.27 1.02 2.57 0.73 0.58 2.28 4 2.11 5 0.48 2.00 0.42 0.08 1.92 0.37 0.14 1.86 8 0.34 0.18 1.82 0.31 0.22 1.78 10 0.29 0.26 1.74 11 0.27 0.28 1.72 12 0.31 1.69 0.25 13 0.24 0.33 1.67 14 0.22 0.35 1.65 15 0.36 1.64 0.21 16 0.38 1.62 17 0.20 0.39 1.61 18 0.19 0.40 1.60 19 0.19 0.41 1.59 20 0.18 23 67
Expert Solution
Step 1

None is the correct answer.

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Optimization
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman