Kite Corp. manufactures custom cabinets and uses a job-order costing system. The company had two jobs in process at the beginning of October: Job No. 64 with a total beginning cost of $56,700 and Job No. 65 with a total beginning cost of $83,300. The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,021,000 and 57,000 machine hours. The company worked on four jobs during the month of October. Direct materials, direct labor incurred, and machine hours consumed were as follows: Direct Material $21,000 Direct Labor $35,000 $22,000 $65,000 $ 8,800 Machine Hours 1,500 Job No. 64 65 900 $44,000 $15,000 66 2,000 67 200 Indirect production costs incurred during October included charges for depreciation ($34,000), indirect labor ($68,000), indirect materials ($5,000), and other factory costs ($139,100). Kite Corp. completed Job No. 64 and Job No. 66 during October. Job 64 was sold on October 22nd.

Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter6: Process Cost Accounting—additional Procedures; Accounting For Joint Products And By-products
Section: Chapter Questions
Problem 6E: Foamy Inc. manufactures shaving cream and uses the weighted average cost method. In November,...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Kite Corp. manufactures custom cabinets and uses a job-order costing system. The
company had two jobs in process at the beginning of October: Job No. 64 with a total
beginning cost of $56,700 and Job No. 65 with a total beginning cost of $83,300.
The company applies manufacturing overhead on the basis of machine hours. Budgeted
overhead and machine activity for the year were anticipated to be $3,021,000 and 57,000
machine hours.
The company worked on four jobs during the month of October. Direct materials, direct
labor incurred, and machine hours consumed were as follows:
Direct Material
$21,000
Machine Hours
1,500
Direct Labor
$35,000
$22,000
$65,000
$ 8,800
Job No.
64
65
900
$44,000
$15,000
66
2,000
67
200
Indirect production costs incurred during October included charges for depreciation
($34,000), indirect labor ($68,000), indirect materials ($5,000), and other factory costs
($139,100). Kite Corp. completed Job No. 64 and Job No. 66 during October. Job 64 was
sold on October 22nd.
Transcribed Image Text:Kite Corp. manufactures custom cabinets and uses a job-order costing system. The company had two jobs in process at the beginning of October: Job No. 64 with a total beginning cost of $56,700 and Job No. 65 with a total beginning cost of $83,300. The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,021,000 and 57,000 machine hours. The company worked on four jobs during the month of October. Direct materials, direct labor incurred, and machine hours consumed were as follows: Direct Material $21,000 Machine Hours 1,500 Direct Labor $35,000 $22,000 $65,000 $ 8,800 Job No. 64 65 900 $44,000 $15,000 66 2,000 67 200 Indirect production costs incurred during October included charges for depreciation ($34,000), indirect labor ($68,000), indirect materials ($5,000), and other factory costs ($139,100). Kite Corp. completed Job No. 64 and Job No. 66 during October. Job 64 was sold on October 22nd.
18.
What is the cost of goods manufactured for the month of October?
a. $350,500
b. $407,200
c. $221,700
d. $345,200
e. $350,800
f. $192,200
g. $408,950
h. None of the above
19.
What is the balance in work in process at the end of October?
a. $104,100
b. $129,100
c. $249,400
d. $187,400
e. $153,000
f. $130,200
g. $402,400
h. None of the above
20.
What is the overhead variance for the month of October?
a. $10,600 under applied
b. $10,600 over applied
c. $5,650 under applied
d. $5,650 over applied
e. $7,950 under applied
f. $7,950 over applied
g. $2,300 under applied
h. $2,300 over applied
i. None of the above
Transcribed Image Text:18. What is the cost of goods manufactured for the month of October? a. $350,500 b. $407,200 c. $221,700 d. $345,200 e. $350,800 f. $192,200 g. $408,950 h. None of the above 19. What is the balance in work in process at the end of October? a. $104,100 b. $129,100 c. $249,400 d. $187,400 e. $153,000 f. $130,200 g. $402,400 h. None of the above 20. What is the overhead variance for the month of October? a. $10,600 under applied b. $10,600 over applied c. $5,650 under applied d. $5,650 over applied e. $7,950 under applied f. $7,950 over applied g. $2,300 under applied h. $2,300 over applied i. None of the above
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning