FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
Bartleby Related Questions Icon

Related questions

Question

Please answer No. 22 and 23

The First Part of Question No. 23 is on the other Picture

Provide a complete solution. Thank You

(1 92,000)
2.JM
'n
SMDC Company has started construction work on a project with a fixed contract
price of P4,000,000. SMDC expects to incur total costs of P3,000,000 on this project.
During the first year of the project, the following transactions occurred:
expand button
Transcribed Image Text:(1 92,000) 2.JM 'n SMDC Company has started construction work on a project with a fixed contract price of P4,000,000. SMDC expects to incur total costs of P3,000,000 on this project. During the first year of the project, the following transactions occurred:
Chapter 8- Long Term Construction Contracts
Incurred cost of materials, labor and overhead used in the work, P2,400,000.
Paid costs of materials purchased but set aside for use in a future date for
this project, P200,000. These materials do not have any alternative use and
cannot be sold to other parties.
Paid and incurred rectification work no expected to be recovered, P260,000.
Incurred general and administrative costs that are not reimbursable,
P100,000.
Incurred selling costs, P60,000.
Incidental income from the sale of certain materiałs, P40,000. These specific
materials were sold since it was considered surplus from the early phase of
the construction.
The engineers determined that the original estimate of costs did not include
any expected warranty costs of P200,000.
23. Determine the profit for the first year.
P600,000
P220,000
a.
P840,000
C.
b.
P715,000
d.
On August 1, 2019, Panglao Construction Company obtain a contract to construct
a low rise building in Taguig City. The building was estimated to cost P17.5M and
is scheduled for completion on October 2021. The contract contains a penalty
clause to the effect that the other party is to deduct P35,000 from the contract price
for each week of delay. Completion was delayed for 5 weeks. Below are the data
pertaining to the construction period.
2019
2020
2021
Costs incurred
Estimated cots to complete
Progress Billings
P1,750,000
7,000,000
1,400,000
P1,085,000
P6,440,000
910,000
15,225,000
4,200,000
24. Using the percentage of completion method, the realized gross profit (loss( for
the 2021 is:
year
P822,500
b. (P35,000)
a.
P840,000
C.
d.
(P122,500)
expand button
Transcribed Image Text:Chapter 8- Long Term Construction Contracts Incurred cost of materials, labor and overhead used in the work, P2,400,000. Paid costs of materials purchased but set aside for use in a future date for this project, P200,000. These materials do not have any alternative use and cannot be sold to other parties. Paid and incurred rectification work no expected to be recovered, P260,000. Incurred general and administrative costs that are not reimbursable, P100,000. Incurred selling costs, P60,000. Incidental income from the sale of certain materiałs, P40,000. These specific materials were sold since it was considered surplus from the early phase of the construction. The engineers determined that the original estimate of costs did not include any expected warranty costs of P200,000. 23. Determine the profit for the first year. P600,000 P220,000 a. P840,000 C. b. P715,000 d. On August 1, 2019, Panglao Construction Company obtain a contract to construct a low rise building in Taguig City. The building was estimated to cost P17.5M and is scheduled for completion on October 2021. The contract contains a penalty clause to the effect that the other party is to deduct P35,000 from the contract price for each week of delay. Completion was delayed for 5 weeks. Below are the data pertaining to the construction period. 2019 2020 2021 Costs incurred Estimated cots to complete Progress Billings P1,750,000 7,000,000 1,400,000 P1,085,000 P6,440,000 910,000 15,225,000 4,200,000 24. Using the percentage of completion method, the realized gross profit (loss( for the 2021 is: year P822,500 b. (P35,000) a. P840,000 C. d. (P122,500)
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education