In the following table, the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working. D Immediate Predecessor(s) Time (days) Activity A B с D E F G H Using the activity-on-node (AON) project network associated with the above table, Carl's team should be able to complete the project in A A B B с D E, F days. 4 6 6 4 4 6 9

Algebra & Trigonometry with Analytic Geometry
13th Edition
ISBN:9781133382119
Author:Swokowski
Publisher:Swokowski
Chapter3: Functions And Graphs
Section3.3: Lines
Problem 76E
icon
Related questions
Question
In the following table, the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working.
Activity
Immediate
Time (days)
7
4
6
6
ABCDEFGH
Using the activity-on-node (AON) project network associated with the above table, Carl's team should be able to complete the project in
Predecessor(s)
AABBU
C
D
E. F
days.
446 O
9
Transcribed Image Text:In the following table, the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working. Activity Immediate Time (days) 7 4 6 6 ABCDEFGH Using the activity-on-node (AON) project network associated with the above table, Carl's team should be able to complete the project in Predecessor(s) AABBU C D E. F days. 446 O 9
Task time estimates for the modification of an assembly line at Robert Klassen's Ontario factory are as follows.
Time
(in hours)
Activity
ABCDEFG
6.0
6.5
4.0
5.0
4.5
7.5
4.0
Immediate
Predecessor(s)
A
B, C
B, C
D
E, F
D
This exercise contains only parts d, b, and c.
d) Use the multipoint curve drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times.
Carefully follow the instructions above, and only draw the required objects.
C
B
C-
D-
E-
F
G-
OS
0
2
4 6
8 10 12 14 16 18 20 22 24 26 28
Transcribed Image Text:Task time estimates for the modification of an assembly line at Robert Klassen's Ontario factory are as follows. Time (in hours) Activity ABCDEFG 6.0 6.5 4.0 5.0 4.5 7.5 4.0 Immediate Predecessor(s) A B, C B, C D E, F D This exercise contains only parts d, b, and c. d) Use the multipoint curve drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times. Carefully follow the instructions above, and only draw the required objects. C B C- D- E- F G- OS 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
Recommended textbooks for you
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
College Algebra (MindTap Course List)
College Algebra (MindTap Course List)
Algebra
ISBN:
9781305652231
Author:
R. David Gustafson, Jeff Hughes
Publisher:
Cengage Learning