7) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 3,344,000 | $ | 3,960,000 | $ | 1,645,600 | |||||
Estimated costs to complete as of year-end | 5,456,000 | 1,496,000 | 0 | ||||||||
Billings during the year | 2,800,000 | 4,504,000 | 2,696,000 | ||||||||
Cash collections during the year | 2,600,000 | 4,400,000 | 3,000,000 | ||||||||
Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross
2-a. In the journal below, complete the necessary
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 2,480,000 | $ | 3,840,000 | $ | 3,280,000 | |||||
Estimated costs to complete as of year-end | 5,680,000 | 3,180,000 | 0 | ||||||||
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 2,480,000 | $ | 3,840,000 | $ | 4,020,000 | |||||
Estimated costs to complete as of year-end | 5,680,000 | 4,180,000 | 0 | ||||||||

Trending nowThis is a popular solution!
Step by stepSolved in 3 steps

- Required information [The following information applies to the questions displayed below.) In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. 2024 2,800,000 700,000 2025 2024 $ 2,100,000…arrow_forwardPlease help with question, thanks.arrow_forwardneed correct and complete answer with explanation , computation , steps in text form please provide explanation and computation clearly for each steps answer in text formarrow_forward
- Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2023 2024 2025 Costs to date (12/31) $1,017,000 $2,928,960 $4,576,500 Estimated costs to complete (12/31) 3,051,000 1,647,540 0 Progress billings during the year 968,000 2,418,000 1,134,000 Cash collected during the year 817,000 1,897,000 1,806,000 The revised estimates for the bridge contract are as follows. 2023 Original Estimates 2024 Revised Estimates Contract price $4,520,000 $4,520,000 Estimated total cost 4,068,000 4,576,500* Estimated gross profit $452,000 Estimated loss $(56,500) *$2,928,960 + $1,647,540 (a1) Under the percentage-of-completion method, calculate…arrow_forwardPlease give working notes and proper explanation of solutionarrow_forwardHansabenarrow_forward
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred…arrow_forwardIn 2021, the Kokosing Construction Company of Columbus, Ohio entered into a contract to construct a road for Franklin County for $20,000,000. The road was completed in 2023. Information pertaining to the contract is provided below: 2021 2022 2023 Costs incurred during the year Estimated costs to complete as of year end Billings during the year Cash Collections during the year $4,800,000 $7,200,000 $4,400,000 11,200,000 4,000,000 4,000,000 8,000,000 8,000,000 3,600,000 7,200,000 9,200,000 Kokosing recognizes revenue over time according to percentage of completion. Required: 1. Compute the amount of revenue and gross profit to be recognized in 2021, 2022, and 2023. 2. Prepare the necessary journal entries for 2021 and 2022. Use the following accounts for your journal entries - "Construction in Progress", "Cash, Materials etc.", "Accounts Receivable", "Billings on Construction in Progress", "Cash", "Cost of Construction", and "Revenue from Long-term contracts". 3. Prepare a partial…arrow_forwardIn 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $ 3,219,000 5,481,000 2,700,000 2,500,000 2025 $ 3,915,000 1,566,000 4,434,000 4,300,000 2026 $ 1,722,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. 0 2,866,000 3,200,000 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.arrow_forward
- 5) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred…arrow_forwardPlease answer competely and properlyarrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,581,000 $2,347,000 $3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to percentage of completion. complete the…arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education