Can someone show me how to balance this using shortesr-time operation rule? and their efficiency too . Im not too sure of my diagram

Transcribed Image Text:+
As Patrick Sportwear Co. completes plans for its new assembly line of Liverpool, it identifies 30
different tasks in the production process. VP of Operations Kevin Keegan now faces the job of
balancing the line. He lists precedences and provides time estimates for each step based on
work-sampling techniques.
His goal is to produce 1.000 football shoes per standard 35-hour workweek.
Task
Time (sec)
Immediate
Predecessors
B1
K4
K9
J1
C2
J2
J3
D5
G4
G5
F3
F4
F7
E1
F9
E2
A4
E3
D6
D7
C1
D8
D9
C3
B3
B5
A1
B7
A2
A3
50
24
27
66
12
22
3
6
79
29
32
92
21
20
126
18
10
109
53
72
78
78
37
40
72
108
52
18
72
114
B1
B1
B1
B1
C2
K4, K9
K9, J1
J2
J2
J3
C2
G4, K4
G5, F3
E1
F3
F4
F9, E2, E3, K9
F7, A4
E3, D6
D6, A4
F9, D7
D7, D8, D9, C1
C1
B5
A1, B3, C3
B5
B7, A1, A2, D5
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps with 1 images

Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
Hello, thanks greatly but why did you use maximum time duration and not shortest time rule in finding the time to make one ball? ( D5 - A14 = 120 SEC )
Solution
by Bartleby Expert
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
Hello, thanks greatly but why did you use maximum time duration and not shortest time rule in finding the time to make one ball? ( D5 - A14 = 120 SEC )
Solution
by Bartleby Expert
Knowledge Booster
Similar questions
- K The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 56 boats. Given the following information: Task A B C D E F FGH 1 Performance Time (mins) 1 1 2 1 3 1 1 2 1 Predecessors a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in Fig. 1 A A C C C D, E, F B G, H Fig. 2 Fig. 3 Fig. 1 Fig. 2 Fig. 3 4 B DA E E F F H Harrow_forwardWhat a re the techniques available to operations managers to deal with a bottleneck operation? Which of these does not decrease throughput time?arrow_forward"Discuss the difference between resource loading and resource leveling, and provide an example of when you would use each technique"arrow_forward
- esign Layout References Mailings Review View Help 、三 目三==。 v11 、 ab х, х* А Normal No Spacing Heading 1 Editing A Aa v A A の、困、 Font Paragraph Styles 1. The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining the figures in the diagram below. la. Compute the labor productivity per worker for each of the six weeks. ( on an excel file with shown formula) Week Crew Size Yards Installed 4 96 3. 72 3. 92 50 69 6. 2. 52 I> 3. 1, 2.arrow_forwardYour class has volunteered to work for Referendum 13 on theNovember ballot, which calls for free tuition and books for allcollege courses except Operations Management. Support forthe referendum includes assembling 10,000 yard signs (pre-printed water-resistant paper signs to be glued and stapled toa wooden stake) on a fall Saturday. Construct a flowchart anda process chart for yard sign assembly. What inputs in termsof materials, human effort, and equipment are involved?Estimate the amount of volunteers, staples, glue, equipment,lawn and garage space, and pizza required.arrow_forward3. A production line must produce 2,500 units every 6 hours of operating time. What is its cycle time in seconds? (Noteshaper Quick Start # 15)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.