Question
Given the following highway rerouting project,
refer to the two pics please :))
(a) Draw the network.
(b) Find the ESs, LSs, and slacks.
(c) Find the critical path.
(d) If the project has a 1 1/2-year deadline for reopening, should we consider crashing some activities? Explain.

Transcribed Image Text:Activity
A: Schedule crew
B: Schedule equipment
C: Plan new route
D: Costs meet budget?
E: Inform public
F: Put out signs
G: Begin rerouting
Immediate
Predecessor
A
B
C, B
C, B
D, E
Activity Time
(months
46266mm 5
4
6
2
6
3
3
5

Transcribed Image Text:Start
Early
Sll
Lak
St
A
006
06
7
Actu
Legend for Solution
Earty
Firtsh
Duralon
7
Lak
Firsty
36
C
9
6012
D
112
6 12
Critical Path
9
芭
9 3 12
12 0 17
G
12 517
14 3 17
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 4 images

Knowledge Booster
Similar questions
- Construct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.arrow_forwardAnalyze the decision to build an amusement park abut a national forest that will not charge an admission for the community to use. Who would fund this type to project.arrow_forwardM7-3 Assignment Use Microsoft Project software to solve this assignment problem. Submit your project file and provide your answers on the attached answer sheet template. Consider the following network with tasks duration in days: TPPM Assignment 7 - Page 13 (Note: Tack is a dummy task. It must be included in the relationships, but its duration is set duration Task Pastimet Lily Optimatic FedCat A 1000 2 • GOO 12 7 2 2500 D 12 800 9 800 24 12 2400 G 11 4 800 H " 5 1200 2 5000 25 17 9 4200 K 3000 L 2500 M 12 30 3000 N 1. Set the Project start on Monday 11/1/20 Thursday 11/26/20, Friday 11/27/20, 12/25/20, and 1/1/21 are holidays 2. Determine critical path and its duration. When the project will end date? 3. There is a possiblity that the starting task K may be delayed by 3 days. Will this impact the project completion date? If yes, when will be the new finish date? (After checking this out, please restore the project to its original schedule). 4. Assign the following resources to the…arrow_forward
- The Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forwardNetwork Analysis Given this WBS, draw out a network diagram and use the two-pass and enumera methods to answer the following questions. Activity LCT 50 - b a-d-g-j Predecessor Ob-f-i Oa-c-f-i a-e-h-j a a a b, c d d, e f g, h <*** Duration 5 days Saved 434 994 6 4 5 Question 6 (1 point) Consider the network above. What is the critical path for this project? 6 6arrow_forwardPlease help to solvearrow_forward
- Identify and briefly discuss at least three (3) risks that may be associated with this project.Kennedy/Brydon Interchange Project The Kennedy/Brydon Interchange has two lanes of traffic coming in from all four directions. For this project the requirement is to: - Create three lanes of traffic coming into the intersection from all four directions - Add center lanes in all four directions coming into the intersection - The new three lanes and center lanes must start a half mile from the intersection in all four directions - The new traffic pattern must blend with existing lane patterns that go into the intersection, from half a mile, in all four directions - The new traffic light signals at the interchange must be synchronized with the next three traffic light signals coming into the interchange, from half a mile, in all four directionsarrow_forwardThe VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a. List the possible eight events which you think essential in expanding a Cinema. b. Draw a network diagram c. find the total time required to complete the project. d. List the critical events of the project. АСTIVITY IMMEDIATE TIME(WEEKS) PREDECESSOR A 3 В 4 A D B 2 E A 5 F 2 D, E 4 H F, G 5arrow_forwardDraw a network diagram, including ES, EF, LS, LF, Float and Duration for the following scenario:arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.