Q: Tarnish Industries produces miniature models of farm equipment. These collectibles are in great…
A: "Since you have asked multiple questions, we will solve first question for you. If you want any…
Q: A manufacturer uses activity-based costing to assign overhead cost to products. Budgeted cost…
A: Using activity based costing, the overhead is applied using different activity rates. The activity…
Q: Kesterson Corporation has provided the following information: Cost per Cost per Direct materials…
A: Variable cost needs to be incurred for each additional unit. Where's fixed cost will remain constant…
Q: A company sells two types of products: standard and deluxe. It prepares the following analysis…
A: Activity Rate :— It is the rate used to allocate manufacturing overhead cost to cost object under…
Q: Required: 1. Compute overhead rates for each of the three activities 2. What is the expected…
A: Given in the question:Budgeted units produced of Standard Units = 36,375 UnitsBudgeted units…
Q: Mona moobl3 Ltd operates a standard costing system and absorbs overheads on the basis of standard…
A: Option b is correct.
Q: SAS co. operates a marginal costing system and sells two products Handbags (H) and Perfumes (P). The…
A: The following computations are done for SAS Company.
Q: Bally Incorporated has identified the following cost drivers for its expected overhead costs for the…
A: Activity Rate :— It is the rate used to allocate manufacturing overhead cost to cost object under…
Q: Monty Company produces chairs and has determined the following direct cost categories and budgeted…
A: Introduction:- Standard costs are estimates of the actual costs in a company’s production process…
Q: Mike. Inc has two products A and B. The budgeted fixed manufacturing overhead is $10,000. The…
A: A predetermined overhead rate is calculated at the start of the accounting period by dividing the…
Q: A company uses activity based costing to divide overheads between its three products and has the…
A: Activity-based costing is used to allocate the indirect expenses to the product on the basis of…
Q: Shilongo Ltd uses costing to attribute costs to individual products and services provided to its…
A: Simultaneous Equation Method: This is method of allocation of overheads costs of the service…
Q: Monty Company produces chairs and has determined the following direct cost categories and budgeted…
A: Introduction:- Standard costs are estimates of the actual costs in a company’s production process…
Q: Manuel Company predicts it will operate at 80% of its productive capacity. Its overhead allocation…
A: Variances are the differences between the actual values and budgeted values. If the budgeted values…
Q: In July 2022, Thembi presented data in Table 3 for her cost center in budget costing: Table 3:…
A: Overhead absorption rate :— It is the estimated overhead rate which is used to apply overhead to…
Q: Standard cost of production in Dagoreti Ltd. is as follows: Time 2 hours per unit…
A: To calculate the labor variances, we first need to calculate the standard labor cost and the actual…
Q: A company has two products: A1 and B2. It uses activity-based costing and has prepared the following…
A: ACTIVITY BASED COSTINGActivity Based Costing is a Powerful tool for measuring…
Q: Cosmo Technology manufactures three products: GX, TY, and KZ. They all use the same resources but in…
A: The question is related to Activity Based Costing. The detais of three products are given. The cosr…
Q: Calculators P/L manufactures two types of products, Advanced and Simple, and applies manufacturing…
A: The activity-based costing approach is a way of allocating overhead and indirect expenses to goods…
Q: Prepare a variance analysis on the Unit Sales, Sales Price, Fixed Overhead and Administration…
A: Given in the question: Budgeted Fixed Overhead Insurance 36000…
Q: Shilongo Ltd uses costing to attribute costs to individual products and services provided to its…
A: Simultaneous Equation Method: This is a method of allocation of Service Departments Overheads Cost…
Q: company produces a unit where delivery of units to its customers are related with all overheads.…
A: Standard costing is a method where it was used to identify variances between actual and budgeted and…
Q: Tina Company manufactures pans. Below is the information related to its direct material costs:…
A: Formulae for labour variance Labour variance = Actual hours *Actual rate - actual hours *standard…
Q: Use a cost-volume graph to determine the type of cost behavior exhibited in Groups A, B, and C. In…
A: Variable Cost - Variable cost is the cost which is per unit fixed and varies with the level of…
Q: BOTE Inc. produces sustainable plastic bottles, The following tables show the detailed production…
A: Activity based costing is a method of costing in which all indirect costs or overheads are allocated…
Q: BesteLippe (Pty) Ltd produces two types of lip balm, namely Healing and Organic and uses an…
A: The objective of the question is to calculate the total budgeted fixed cost to be used in the…
Q: Lawn RX, Inc. prepares a variable costing income statement for internal management and an absorption…
A: Unit Product Cost = Direct Labor Cost + Variable Cost + Fixed Cost
Q: Mike. Inc has two products A and B. The budgeted fixed manufacturing overhead is $10,000. The…
A: Step1 Net Income Per unit, the measure indicates how a particular product contributes to the overall…
Q: j2j
A: Step 1: Understanding the Information givenDirect labour hours:Wall Mirrors: 1,100Specialty Windows:…
Q: A company sells two types of products: standard and deluxe. It prepares the following analysis…
A: An organization's activities are identified using the activity-based costing (ABC) technique, which…
Q: A company has two products: A and B. It uses activity-based costing and has prepared the following…
A: Activity-based costing is a costing approach in which a company's activities are identified and the…
Q: Mike. Inc has two products A and B. The budgeted fixed manufacturing overhead is $10,000. The…
A: Given Information:
Q: Benson Manufacturing Company established the following standard price and cost data. $ 8.00 per unit…
A: The master budget is based on planned units and standard costs.The flexible budget is based on…
Q: Julum Limited manufactures a single product and operates a standard costing system. Budgeted…
A: Labour cost variance means difference of budgeted cost of labour and actual cost of labour. It can…
Q: Hpany has two products: A1 and B2. It uses activity-based costing and has prepared the following…
A: Activity-based costing helps to allocated overhead effectively into the different cost pools. It is…
Q: question: 1. If allocating fixed manufacturing overhead based on direct labor hour basis, calculate…
A:
Q: Under absorption costing, a company had the following unit costs when 13,500 units were produced.…
A: Absorption (full) costing: Absorption (full) costing is a costing technique in which all the…
Q: The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity)…
A: The variance is the difference between the costs estimated and the actual costs incurred. If the…
Q: Consider the following data for two products of Vigano Manufacturing. Budgeted Cost Activity Machine…
A: Product cost is the amount of cost incurred by the entity on the making of the goods. These include…
Q: ble manufacturing overhead manufacturing overhead t labor-hours ement is considering a special the…
A: To decide whether the special order must be accepted or not, the relevant cost and revenue is…
Q: detail for its activities and its product at the start of the period: Budgeted overhead = £400,000…
A: The overhead is applied to the production on the basis of predetermined overhead rate. The overhead…
Q: Schwiesow Corporation has provided the following information: Direct materials Direct labor Cost per…
A: In accounting manufacturing overhead refers to all those indirect costs that are incurred during the…
Q: Activity Rates Patten Company uses activity-based costing (ABC). Patten manufactures toy cars using…
A:
Q: KENT Ltd produces a range of products. Manufacturing is undertaken using one of two processes: the…
A: Kent produces two products: 1. JT101 2. GR27 We are provided with a total set up cost= of 85800…
Q: Julum Limited manufactures a single product and operates a standard costing system. Budgeted…
A: The variance is the difference between standard data and actual cost.
Q: Matolo ltd manufactures two types of products BELL and CELL.The following budgeted information is…
A: Activity based costing is the method which determines the overhead rate by identifying and…
Gemma Co uses activity based costing to divide overheads between its two products and has the following budgeted information
|
S |
T |
Production level |
80,000 |
120,000 |
Set-ups per batch |
4 |
2 |
Batch size |
5,000 |
4,000 |
Budgeted set-up costs are £74,400
Calculate the cost per set-up and the set-up cost per unit for product T.
Step by step
Solved in 2 steps
- Spree Party Lights overhead expenses are: Indirect material, pounds per unit Indirect material, cost per pound Indirect labor hours Indirect labor rate per hour Variable maintenance per unit Variable utilities per unit Supervisor salaries Maintenance salaries Insurance Depreciation Units to Produce Variable Costs Indirect Material Indirect Labor Maintenance Prepare a manufacturing overhead budget if the number of units to produce for January, February, and March are 2,400, 3,100, and 2,800, respectively. Spree Party Lights Manufacturing Overhead Budget For the Quarter Ending January - March January February 2,400 3,100 Utilities Total Variable Manufacturing Costs Fixed Costs 0.30 Supervisory Salaries Maintenance Salaries Insurance Depreciation Total Fixed Manufacturing Coats Total Manufacturing Overhead $2 $16.50 $0.75 $0.20 $11,000 $9,000 $3,000 $1,600 1,440 30,500 1.1900 11,000 5,000 3,000 1,500 24,600 67,020 1,860 51,150 620 53,955 11,000 9,000 3,000 1,000 24,400 10,355 March 2,1800…Mona moobl3 Ltd operates a standard costing system and absorbs overheads on the basis of standard labour hours. There were 500,000 labour hours budgeted and the budgeted production overheads were GH¢300,000 for the forthcoming year. The company budgeted to produce 125,000 units. The actual results for the period were as follows: Overheads-GH¢350,000, Output-130,000 units and Labour hours 450,000 hours. Which ONE of the following statements is correct? A. Overheads were GH¢38,000 over-absorbed. B. Overheads were GH¢38,000 under-absorbed. C. Overheads were GH¢80,000 over-absorbed. D. Overheads were GH¢80,000 under-absorbed. Reset Selection ▲ Question Progress ▲Spree Party Lights overhead expenses are: Indirect material, pounds per unit Indirect material, cost per pound Indirect labor hours Indirect labor rate per hour Variable maintenance per unit Variable utilities per unit Supervisor salaries Maintenance salaries Insurance Depreciation Units to Produce Variable Costs Indirect Material Indirect Labor Maintenance Prepare a manufacturing overhead budget if the number of units to produce for January, February, and March are 2,400, 2,900, and 2,600, respectively. Spree Party Lights Manufacturing Overhead Budget For the Quarter Ending January - March January February Utilities Total Variable Manufacturing Costs Fixed Costs Supervisory Salaries Maintenance Salaries Insurance Depreciation 0.30 $2 1 Total Fixed Manufacturing Costs Total Manufacturing Overhead $16.00 $0.75 $0.20 $9,000 $8,000 $4,000 $1,400 March
- A manufacturer uses activity-based costing to assign overhead cost to products. Budgeted cost information for its activities follows. Budgeted Cost $ 210,600 Activity Cost Driver Purchase orders Square feet Budgeted Activity Usage 5,400 purchase orders 5,900 square feet 50 Setups Factory services 104,250 Setup 67,750 Setups Compute an activity rate for each activity. (Round your answers to 2 decimal places.) Activity Purchasing Activity Purchasing Factory services Setup Budgeted Cost 210,600 104,250 67,750 $ $ $ Budgeted Activity Usage Activity RateMaria Company uses both standards and budgets. For the year, estimated production of Product X is 597,000 units. Total estimated cost for materials and labor are $1,194,000 and $1,671,600respectively.Compute the estimates for (a) a standard cost and (b) a budgeted cost. (Round standard costs to 2 decimal places, e.g. 1.25.) Materials Labor (a) Standard cost $enter a dollar amount rounded to 2 decimal places $enter a dollar amount rounded to 2 decimal places (b) Budgeted cost $enter a dollar amount $enter a dollar amountThe following variable production costs apply to goods made by Fanning Manufacturing Corporation: Item Materials Labor Variable overhead Total Required Determine the total variable production cost, assuming that Fanning makes 10,000, 20,000, or 30,000 units. Units Produced Cost per Unit $10.00 2.50 0.75 $13.25 Total variable cost 10,000 20,000 30,000
- Shilongo Ltd uses costing to attribute costs to individual products and services provided to its customers. It has begun the preparation of its fixed production cost budget for the forthcoming period. The company three production departments Machining, Assembly and Finishing; and two service departments Stores and Maintenance. The following costs have been produced: Machining Assembly Finishing Stores Maintenance 2,500 1,500 1,000 Overhead cost $ 6,000 800 The number of machine and labor hours budgeted for the forthcoming period is budgeted as follows:- Machining Assembly Finishing Machine hours 500 40 50 Labor hours 100 300 200 Overheads are absorbed in Assembly and Finishing departments on a Labor hour basis; and in Machining departments they are absorbed on a machine hour basis. It has been estimated that service departments usage is as follows: Machining Assembly Finishing Stores Maintenance Maintenance 55% 20% 20% 5% - Stores 40% 30% 20% 10% Required: b) Calculate the overhead…Julum Limited manufactures a single product and operates a standard costing system. Budgeted Data (per unit) : Labour 5 hours @ £15.00 Per Hour Budgeted production for August was expected to reach 10000 Units Actual production 11000 Units The actual costs incurred were as follows : Actual Data : Labour 60000 hours @ £14.50 Per Hour a. What is Labour Rate Variance? Choose one from the following: A. £30,000.00 Favourable B. £75,000.00 Unfavourable C. £45,000.00 Favourable D. £45,000.00 UnfavourableCosting information for Emily Elephant Limited is as follows:Direct material cost per unitDirect labour cost per unitVariable manufacturing overhead cost per unitVariable selling and administrative overhead cost per unitFixed manufacturing overhead for the year£41 £43£6£4£44,000Budgeted production for the year was 4,000 units. What is the budgeted unit product cost according to an absorption costing system? a. £90 b. £101 c. £105d. £94
- Perez Manufacturing Company established the following standard price and cost data. Sales price Variable manufacturing cost $ 8.98 per unit $ 3.40 per unit Fixed manufacturing cost Fixed selling and administrative cost $ 2,000 total $ 600 total Perez planned to produce and sell 2,300 units. Actual production and sales amounted to 2,600 units. Required a. Prepare the pro forma income statement in contribution format that would appear in a master budget. b. Prepare the proforma Income statement in contribution format that would appear in a flexible budget. Complete this question by entering your answers in the tabs below. Required A Required B Prepare the pro forma income statement in contribution format that would appear in a master budget. PEREZ MANUFACTURING COMPANY Pro Forma Income Statement Master Budget 2,300 UnitsThe following data are given for Stringer Company: Budgeted production Actual production Materials: Standard price per ounce Standard ounces per completed unit Actual ounces purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs 907 units 1,033 units $1.91 11 11,704 $23,993 $14.84 per hour 4.6 5,319.95 $81,129 Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs Overhead is applied on standard labor hours. Do not round interim calculations. Round your final answer to the nearest dollar. The direct materials price variance is $1,071,000 $28.00 per standard labor hour $148,959Zizi plc uses a standard absorption costing system and produces and sells product 8W. The standard cost card is below: Product 8W (€ per unit) Direct material (5 per kg) 15 Direct labour (6 per hour) 12 Fixed manufacturing overhead 10 Total production cost 37 Standard profit 13 Standard selling price 50 * Absorption rate based on standard labour hours Budgeted and actual production and sales units for december 2020 were as follows: Budget Actual Production 1,100 900 Sales 1,000 800 Actual data for December 2020 were as follows € Direct material purchases 1,200 kgs costing 12,000 Direct materials used 1,100 kgs Direct labour hours 500 hours costing 6,000 Fixed manufacturing overhead 5,000 Sales revenue 30,000 An analysis of the Direct labour hours shows that the 500 hours that were paid for 50 were idle time due to a machinery breakdown. There were no inventories of Direct materials or finished products (planned or actual) at the…