What is the node network diagram & critical path for this
**Activity on Node Diagram: Critical Path Analysis**

For the activity on node shown, find the critical path and the expected duration of the project.

**Note:** P, x = Activity, duration in weeks

### Diagram Description:

The diagram is a network graph representing project activities and their durations. Each activity is labeled with a letter and a number indicating its duration in weeks. The nodes represent different stages of the project, connected by directed arrows showing the sequence of activities.

- **A (2 weeks):** Starts the project, leading to Activity B.
- **B (3 weeks):** Follows Activity A, leading to Activities C, D, and G.
- **C (1 week):** Concurrent with Activity D, leads to Activity E.
- **D (3 weeks):** Concurrent with Activity C, leads to Activity F.
- **E (4 weeks):** Follows Activity C, converges with F to lead to Activity I.
- **F (3 weeks):** Follows Activity D, converges with E to lead to Activity I.
- **G (2 weeks):** Follows Activity B, leading to Activity H.
- **H (5 weeks):** Follows Activity G, converges with other paths at the final node.
- **I (3 weeks):** Final activity, completes the project.

### Instructions:

Identify the longest path through the network to determine the critical path and calculate the total duration of the project. The critical path will be the sequence of activities that determines the project's minimum completion time.
expand button
Transcribed Image Text:**Activity on Node Diagram: Critical Path Analysis** For the activity on node shown, find the critical path and the expected duration of the project. **Note:** P, x = Activity, duration in weeks ### Diagram Description: The diagram is a network graph representing project activities and their durations. Each activity is labeled with a letter and a number indicating its duration in weeks. The nodes represent different stages of the project, connected by directed arrows showing the sequence of activities. - **A (2 weeks):** Starts the project, leading to Activity B. - **B (3 weeks):** Follows Activity A, leading to Activities C, D, and G. - **C (1 week):** Concurrent with Activity D, leads to Activity E. - **D (3 weeks):** Concurrent with Activity C, leads to Activity F. - **E (4 weeks):** Follows Activity C, converges with F to lead to Activity I. - **F (3 weeks):** Follows Activity D, converges with E to lead to Activity I. - **G (2 weeks):** Follows Activity B, leading to Activity H. - **H (5 weeks):** Follows Activity G, converges with other paths at the final node. - **I (3 weeks):** Final activity, completes the project. ### Instructions: Identify the longest path through the network to determine the critical path and calculate the total duration of the project. The critical path will be the sequence of activities that determines the project's minimum completion time.
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Structural Analysis
Civil Engineering
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:Cengage,
Text book image
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning